Walkway cover near Tung Wah Eastern Hospital
Project Description:
The objective of the proposed works is to enhance the walking environment for people travelling to and from the Tung Wah Eastern Hospital. The works mainly comprise of the construction of a walkway cover about 80 meters in length along Eastern Hospital Road connecting Tung Wah Eastern Hospital and the adjacent bus stops, and associated roads and drainage, geotechnical, utilities diversion, lighting, landscaping, electrical and mechanical works, etc.
Construction Commencement Date:
June 2026
Anticipated Commissioning Date:
2th Quarter of 2028
Contract(s):
Contract No. HY/2025/06
| Contract Title | Construction of Walkway Covers near Princess Margaret Hospital, Tung Wah Eastern Hospital, Castle Peak Hospital and Siu Lam Hospital, Wah Sing Street Escalator Link System, and Lift and Pedestrian Walkway System between Lau Sin Street and Tin Hau Temple Road |
| Commencement Date |
June 2026 |
| Anticipated Completion Date | 4th Quarter of 2029 |
| Contract Sum ($M) | HK$133.98 Million |
| Contractor | Grand View – Excel JV |
| Resident Engineer | Mannings (Asia) Consultants Limited |
Consultant:
Mannings (Asia) Consultants Limited