Contract No. HY/2009/19
(Public Works Programme Item No. 579TH)
Highways Department Central – Wan Chai Bypass – Tunnel (North Point Section) and Island Eastern Corridor Link Not applicable 12:00 noon on Friday, 3 September 2010
(Extended from 12:00 noon on Friday, 30 July 2010)

Description

The works mainly comprise:

  1. construction of a 300m section of tunnel in North Point at the East Portal;
  2. construction of an approach road to the tunnel;
  3. modification of Island Eastern Corridor between Hing Fat Street and Po Leung Kuk Yu Lee Mo Fan Memorial School;
  4. modification of Victoria Park Road and Hing Fat Street junction, and adjacent roadworks;
  5. construction of sub-structures for the Administration Building and East Ventilation Building;
  6. demolition of Rumsey Street Flyover eastbound down ramp in Central; and
  7. associated works including landscaped deck, noise barriers, noise semi-enclosures, road drainage and landscaping works.

The works are expected to commence in September 2010 for completion in 2017.

Submission of Tenders

Tenders must be clearly marked with the tender reference and the subject of the tender on the outside of the envelope (but should not bear any indication which may relate the tender to the tenderer) addressed to the Chairman, Central Tender Board, and placed in the Government Secretariat Tender Box situated in the lift lobby on the lower ground floor of the Central Government Offices (East Wing), 20 Lower Albert Road (at its junction with Garden Road), Hong Kong.  Late tenders will not be accepted.