Hiram’s Highway Improvement Stage 1

Project Description:

To improve two sections of Hiram’s Highway between Clear Water Bay Road and Pak Wai, the existing Ho Chung Road and Luk Mei Tsuen Road.

The proposed improvement works will relieve the traffic congestion on the road section near Marina Cove, enhance the safety of the road section and improve the local access to Ho Chung and Luk Mei Tsuen.

Estimated Project Cost:

HK$1.77 Billion

Construction Commencement Date:

Mar 2016

Anticipated Commissioning Date:

End 2020

Consultant:

Meinhardt Infrastructure and Environment Limited (Design and Construction)

Contract(s):

Contract No. HY/2014/16

Scope Hiram’s Highway Improvement between Clear Water Bay Road and Marina Cove
Commencement Date Mar 2016
Anticipated Completion Date End 2020
Contract Sum HK$1.26 Billion
Contractor China State Construction Engineering (Hong Kong) Limited
Resident Engineer Meinhardt Infrastructure and Environment Limited

More information can be found in the contract website.