Widening of Western Section of Lin Ma Hang Road between Ping Yuen River and Ping Che Road

Project Description:

The proposed project is to widen about 750m of Lin Ma Hang Road between Ping Yuen River and Ping Che Road to cope with the anticipated traffic demand arising from the opening of Frontier Closed Area.

Estimated Project Cost:

HK$ 432.3 Million

Construction Commencement Date:

14 February 2020

Anticipated Commissioning Date:

Fourth quarter of 2023

Contract(s):

Contract No. HY/2019/04

Scope To widen about 750m of Lin Ma Hang Road between Ping Yuen River and Ping Che Road
Commencement Date 14 February 2020
Anticipated Completion
Date
Fourth quarter of 2023
Contract Sum HK$224.06 Million
Contractor China Geo-Engineering Corporation
Resident Engineer Ove Arup & Partners Hong Kong Ltd

Consultant:

Ove Arup & Partners Hong Kong Ltd

Other Related Information: