Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling - Stage 2
Project Description:
To alleviate the traffic congestion problem on Fanling Highway.
Widening of Fanling Highway between Tai Hang and Wo Hop Shek Interchange from dual three-lane to dual four-lane carriageway with hard shoulders; widening of associated slip road at Wo Hop Shek Interchange; realignment of sections of Tai Wo Service Road West and Tai Wo Service Road East; demolition and reprovision of existing footbridges and vehicular bridge; installation of noise barriers; provision of traffic control and surveillance system; and ancillary works.
Estimated Project Cost:
HK$4.32 Billion
Construction Commencement Date:
Jul 2013
Commissioning Date:
August 2019
Contract(s):
Contract No. HY/2012/06
Scope | Widening of Fanling Highway between Tai Hang and Wo Hop Shek Interchange |
Commencement Date | Jul 2013 |
Anticipated Completion Date | 2019 |
Contract Sum | HK$2.51 Billion |
Contractor | China State Construction Engineering (Hong Kong) Limited |
Resident Engineer | Hyder-Arup-Black & Veatch Joint Venture |
More information can be found in the contract website.
Consultant:
Mott Connell Limited(Preliminary Design)
Hyder-Arup-Black & Veatch Joint Venture(Design and Construction)