Elevated Pedestrian Corridor in Yuen Long Town connecting with Long Ping Station

Project Description:

To relieve the prevailing pedestrian congestion on at grade footpaths and to meet the anticipated pedestrian traffic demand to be induced by the future developments in the Yuen Long town area.

Construction of an approximately 540m long covered elevated pedestrian corridor along the Yuen Long Town Nullah from the West Rail Long Ping Station to the south of Kau Yuk Road.

More information can be found in the project website.

Estimated Project Cost:

HK$ 1.70 Billion 

Anticipated Construction Commencement Date:

2019

Anticipated Commissioning Date:

2024

Current Situation:

Tender assessment is in progress

Consultant:

Ove Arup & Partners Hong Kong Ltd