Hong Kong Link Road (HKLR)

Project Description:

The project involves construction of the HKLR which will connect the Main Bridge with the Hong Kong Boundary Crossing Facilities (HKBCF).

The HKLR will comprise sea viaducts in the western waters of Hong Kong, tunnels through Scenic Hill and underneath the Airport Road and Airport Express Line, and at-grade roads on reclamation along the east coast of Airport Island.

More information can be found in the project website.

Project progress photos can be found in the HZMB project website. Please click

Estimated Project Cost:

HK$25.0 Billion

Construction Commencement Date:

May 2012

Anticipated Commissioning Date:

Target to achieve readiness for commissioning by end 2017

Contract(s):

Contract No. HY/2011/03

Scope Design and construction of the section of HKLR between Scenic Hill and the HKBCF, and roadlinks between the HKBCF and Hong Kong International Airport
Commencement Date May 2012
Anticipated Completion Date Target to achieve readiness for commissioning by end 2017
Contract Sum HK$8.88 Billion
Contractor China State Construction Engineering (Hong Kong) Limited
Resident Engineer Ove Arup & Partners Hong Kong Limited

More information can be found in the contract website.

Contract No. HY/2011/09

Scope Design and construction of the section of HKLR between the HKSAR boundary and Scenic Hill
Commencement Date May 2012
Anticipated Completion Date Target to achieve readiness for commissioning by end 2017
Contract Sum HK$12.9 Billion
Contractor Dragages-China Harbour-VSL Joint Venture
Resident Engineer Ove Arup & Partners Hong Kong Limited

More information can be found in the contract website.

Consultant:

Ove Arup & Partners Hong Kong Limited — design and construction

Other Related Information :