PEAKO ENGINEERING CO., LTD
CONTRACT NO. HY/2002/08
Footbridge and Improvements to Ap Lei Chau
Bridge Road & Ap Lei Chau Drive
MONTHLY
ENVIRONMENTAL MONITORING
&
AUDIT REPORT
REPORT
NO. 06
Document
No. R/2647/007 Issue 1
November
2003

Babtie Asia

CONTRACT NO.
HY/2002/08
FOOTBRIDGE AND IMPROVEMENTS TO AP LEI CHAU BRIDGE ROAD
AND AP LEI CHAU DRIVE
MONTHLY ENVIRONMENTAL MONITORING & AUDIT REPORT
REPORT NO. 06
CONTENTS
EXECUTIVE SUMMARY
1.0
ENVIRONMENTAL STATUS
1.1 Background
1.2
Project
Organization & Contact Details of Key Personnel
1.5
Scope of
Works
1.6
Works
Undertaken during the Reporting Period with Illustrations
1.7
Project
Area, Sensitive Receivers & Monitoring Locations
2.0
IMPLEMENTATION STATUS
2.2 Advice on the Implementation Status of
Environmental Protection & Pollution Control / Mitigation Measures
2.2.1 Construction Noise Mitigation Measures
3.0 MONITORING
RESULTS
3.1 Graphical Plots of the Monitored Parameters
3.2 Major Activities During the Reporting Period
3.3 Noise Monitoring Methodology
3.4 Noise Monitoring Equipment
3.6 Noise Parameters Monitored
3.8 Monitoring Date, Time, Frequency and Duration
3.10 Weather Conditions
3.11 Influencing Factors
3.12 Graphical Plots of Trends of Monitored Parameters
4.0 RECORD OF NON-COMPLIANCE OF THE ACTION AND LIMIT LEVELS,
COMPLAINTS, NOTIFICATIONS OF SUMMONS AND SUCCESSFUL PROSECUTIONS
4.1 Non-compliance
of the Action and Limit Levels
4.1.1 Noise
4.2 Written Complaints and Verbal Complaints
4.3 Description of the Actions Taken
4.4 Notifications of Summons and Successful Prosecutions
4.5 Review of the Reasons for
the Implications of Non-compliance & Complaints
5.0 SITE
ENVIRONMENTAL AUDIT RESULTS
5.1
Site
Inspection by Environmental Team (ET)
5.2
Corrective
actions by Contractor
6.0 OTHERS
6.2 Advice on the Solid and Liquid Waster
Management Status
6.2.1 General Refuse
6.2.2 Liquid Waste Management
APPENDICES
Appendix A Construction
Programme
Appendix B Site Organization
Chart
Appendix C Record Photos for
Construction Activities in October 2003
Appendix D The Project Area,
Environmental Sensitive Receivers and the Locations of the Monitoring Stations
Appendix E Calibration
Certificates for Sound Level Meter
Appendix F Data of Noise Monitoring
Appendix G Graphical
Representation of Construction Noise Monitoring Data
Appendix H Weather Conditions
& Major Activities during the Monitoring Period
Appendix I Action &
Limit Levels
Appendix J Graphical Plots of
Trends of Monitored Parameters
Appendix K Construction Noise
Monitoring and Site Audit Schedules
Appendix L Cumulative Statistics on Environmental Complaints
EXECUTIVE SUMMARY
This is the sixth EM & A Report for the project of
Footbridge and Improvements to Ap Lei Chau Bridge Road & Ap Lei Chau Drive.
This report mainly presents the EM & A works
undertaken for the above project from 1 October 2003 to 31 October 2003 in
accordance with the EM & A Manual and the Environmental Permit (EP
130/2002) under the Appendix H of the Particular Specification.
Breach of AL Levels
Leq (30min) noise level measurement was
performed at four monitoring points namely M1, M2,
M3 and M4. M1 is for the Ap Lei Chau Baptist Kindergarten (NSR Ref. no.10). M2 is
for the Harbour Mission Church and Yan Oi Kindergarten (NSR Ref. no. 12). M3 is
for the Hong Kong True Light College (NSR Ref. no. 17). M4 is for the Shan On
House (NSR Ref. no. 20). Since the sensitive receivers on M1, M2 and M3 are for
educational uses, the noise limit level is 70 dB(A) during normal school hours
and 65 dB(A) during examination period. For the sensitive receiver on M4, the
noise limit level is 75 dB(A) as it is a domestic premise.
The
construction noise monitoring was conducted on the 2nd, 8th,
16th, 22nd and 30th of October 2003. All the
measured noise levels at the three monitoring stations (M1, M2 and M4) were
below the noise limit level. ET is seeking for EPD¡¦s approval on the new
exceedance level at noise monitoring station at M3, True Light College in
accordance with Clause 3.7 in the EM&A Manual.
Complaint log & Others
No verbal or written complaints were received
during the reporting period. No notifications of summons, no successful
prosecutions were received during the reporting period.
Future Key Issues
Adverse influence on both air quality and noise level is anticipated
from future construction activities. The Contractor should carry out good site
practice to minimise the potential construction dust and noise pollution.
The Contractor should exert himself to eliminate
the presence of accumulation of stagnant water to avoid the breeding of
mosquitoes and the spread of dengue fever. Surface runoff especially generated
from mini-piling works should be properly treated through sedimentation tank
prior to discharging to stormwater drain.
To improve the hygiene condition of the site, the
Contractor should provide rubbish bins where necessary and remove the rubbish,
if any, within the site area.
Peako
Engineering Co. Ltd was commissioned by the Highways Departments to execute the
Project ¡§Footbridge and Improvements to Ap Lei Chau Bridge Road and Ap Lei Chau
Drive¡¨.
Babtie Asia
Ltd was employed by the Contractor to act as the Environmental Team for this
project. The Independent Environmental Checker is BMT Asia Pacific Limited.
The purpose
of this report is to document the Environmental Monitoring & Audit (EM
& A) works in the period between 1 October 2003 and 31 October 2003.
Titles,
names and contact telephone numbers of the key personnel of the captioned
project are tabulated below:
|
Title |
Name |
Contact Number |
|
Engineer¡¦s Representative (Highways Department) |
Mr. W.
M. Chan |
2231
5722 |
|
EPD |
Mr.
Elvis Au |
2835
1964 |
|
Project Director (Contractor) |
Mr.
Ronnie Lo |
9144
8398 |
|
Project
Manager (Contractor) |
Mr. Steve C L Liu |
9551 1401 |
|
Site
Agent (Contractor) |
Mr. C.
P. Lam |
8206 8280 |
|
Environmental
Team Leader (Babtie
Asia Limited) |
Mr.
Mark Cheung |
2880
9788 |
|
Independent Environmental
Checker (BMT
Asia Pacific Limited) |
Ms.
Lyn Ip |
2241 9812 |

The project organization and lines
of communication with respect to the environmental monitoring works is shown
below.
The whole project will involve four key construction stages:
¡P
footbridge
construction;
¡P
retaining
wall construction;
¡P
road
construction; and
¡P
drainage
works
The overall construction period will be about 20 months. Night-time works
are not expected during the construction phase of the Project.
The latest construction programme is attached in Appendix A. This
construction programme is subject to continuous refinement.
The site
organization chart is shown as Appendix B.
The works for this project are divided
into five major items
Item 1 ¡V Junction
improvements to J/O Ap Lei Chau Bridge Road / Ap Lei Chau Drive, Ap Lei Chau
Drive / Ap Lei Chau Praya Road, and widening of Ap Lei Chau Drive.
Item 2 ¡V Construction
/ modification of the footpaths and central reserves at Ap Lei Chau Bridge
Road, Ap Lei Chau Drive, and Lei Tung Estate Road.
Item 3 ¡V Construction
/ modification of the retaining walls at Ap Lei Chau Bridge Road for the
construction of a staircase, a ramp and an elevated footpath.
Item 4 ¡V Construction
of a footbridge at Ap Lei Chau Bridge Road.
Item 5 ¡V Ancillary
works including slope works, landscaping works and drainage works.
The works undertaken in October 2003
were as follows:
¡P
Shotcreting
and soil nail installation on existing slope at Ap Lei Chau Drive
¡P
Slope
cutting on existing slope
¡P
Road
construction at Ap Lei Chau Drive (Uphill Site)
¡P
Commencement
of Mini-piling
The photos showing the above works are
shown in Appendix C.
The
drawings showing the project area, noise sensitive receivers (NSRs) and the locations
of the monitoring stations are shown in Appendix D.
The
construction noise monitoring stations are M1, M2, M3 and M4.
M1
is for the Ap Lei Chau Baptist Kindergarten (NSR Ref. no.10). M2 is for the
Harbour Mission Church and Yan Oi Kindergarten (NSR Ref. no. 12). M3 is for the
Hong Kong True Light College (NSR Ref. no. 17). M4 is for the Shan On House
(NSR Ref. no. 20).
It
is noted that the locations of the monitoring stations are the same as those
adopted in the Noise Baseline Monitoring.
Impacts on the nearby sensitive receivers were
identified during various construction stages. Appropriate mitigation measures
such as use of quiet plant, reducing percentage on time, avoidance of
simultaneous noisy activities have been recommended to reduce the associated
impacts.
According to the EIA report, the
following should be implemented during the construction period.
|
Location |
Reference Section |
Recommended Environmental Protection Measures |
Responsibility |
|
Construction
Noise Mitigation Measures |
|||
|
Various
Locations and work sites within the project limit |
Section
5.2.4 & 5.2.5 of EIA Report |
Reduce
the nuisance from Construction Noise ¡P
Adopt good site practice and proper site management,
e.g. plant shall be well maintained and mobile plant shall be sited away from
NSRs; ¡P
Use of quiet plant, such as dump truck, grader,
breaker and excavator, and working methods; ¡P
Control the number of equipment operating
concurrently; ¡P
Reduce the operating time of particular noisy
plant on site, e.g. shutting down machines between work periods; ¡P
Monitor noise levels from particularly noisy
activities; and if non-compliance with EIAO-TM standards is observed,
Contractor shall reduce the number of operating plant or re-adjust working
schedule to reduce the impact. |
Highways
Department and Contractor |
|
Location |
Reference Section |
Recommended Environmental Protection Measures |
Responsibility |
|
Construction
Dust Mitigation Measures |
|||
|
Various
Locations and work sites within the project limit |
Section
6.2.2 of EIA Report |
Reduce
the nuisance of Construction Dust ¡P
Follow the guidelines and regulatory requirements
of Air Pollution Control (Open Burning) Regulation and Air Pollution Control
(Construction Dust) Regulation; ¡P
Adopt appropriate environmental pollution control
measures on-site, such as, apply water sprays, use clean impervious sheeting
to cover dusty materials and set minimum practical height for dropping
materials. |
Highways
Department and Contractor |
2.2.1 Construction Noise Mitigation Measures
The Contractor should use silencers or mufflers on construction
equipment such as pneumatic breaker and have air compressors enclosed to avoid
exceeding the noise limit and causing nuisance to the nearby sensitive
receivers.
Regular maintenance of the construction plant is
strongly encouraged to avoid black smoke and excessive noise production. The
machines and plant should be shut down or throttled down to a minimum when they
are in intermittent use.
The plant known to emit noise strongly in one direction
should be orientated to direct noise away from nearby noise sensitive
receivers. The mobile plants should be sited as far away from the noise
sensitive receivers as possible.
It is important to control
the simultaneous operation of the construction plant on site to avoid the
potential noise limit exceedance and nuisance to the nearby sensitive receivers
especially for those which are for educational purpose.
The graphical presentations of the monitored parameters during the reporting period are shown in Appendix G.
Major
activities during October 2003 include the following:
¡P
Shotcreting
and soil nail installation on existing slope at Ap Lei Chau Drive
¡P
Slope
cutting on existing slope
¡P
Road
construction at Ap Lei Chau Drive (Uphill Site)
¡P
Commencement
of Mini-piling
The construction
noise monitoring was carried out by using a Sound Level Meter to ensure that
exceedance in noise levels could be readily identified and timely action taken
to reduce the noise levels within allowable limits.
The
sound lever meter was mounted on a tripod at a height of 1.2m above the ground
level. This was positioned at least 1m away from any nearby reflective
surfaces. During the noise data collection, a portable wind speed meter is
adopted to check the wind speed.
Noise
monitoring would be cancelled in the presence of fog, rain and wind with a
steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s.
At the
end of the monitoring period, the Leq, L10 and L90
were recorded. The site conditions and noise sources were recorded on a standard
record sheet.
The
approved integrating Sound Level Meter, Model No. NA-27, in compliance with the
International Electrotechnical Commission Publication 651:1979 (Type 1) and
804:1985 (Type 1) specification as referred to in the Technical Memorandum
issued under the Noise Control Ordinance (NCO), was used for construction noise
measurement.
The Sound Level Meter has recently been taken to a
laboratory for calibration. The certificate is shown in Appendix E.
A sound level calibrator, Model No. NC-73, was used
to calibrate the Sound Level Meter before and after the measurement on site.
The certificate is shown in Appendix E
The construction noise levels
were measured in terms of equivalent A-weighted sound pressure level (Leq)
measured in decibels (dB).
Leq(30min) was used
as the monitoring parameter for the time period between (0700 to 1900) hours on
normal weekdays.
The two statistical sound levels
LA10 and LA90, the level exceeded for 10 and 90 percent
of the measurement time respectively, were also recorded as supplementary
information for reference.
The noise baseline monitoring
was conducted at four noise sensitive receivers as stated below.
|
Monitoring
Location |
Noise
Sensitive Receiver |
Ref.
No. in the EIA Report |
|
M 1 |
Ap Lei
Chau Baptist Kindergarten |
10 |
|
M 2 |
The
Harbour Mission Church and Yan Oi Kindergarten |
12 |
|
M 3 |
The
Hong Kong True Light College |
17 |
|
M 4 |
Shan
On House |
20 |
All
the monitoring points are at façade. Hence, no correction of data is required.
Locations
of construction noise monitoring stations and photos are shown in Appendix D.
The monitoring frequency will
depend on the scale of the construction activities. The following was adopted
as an initial arrangement of measurement on the regular monitoring frequency
for each station on a per week basis when noise generating activities are
underway:
(a)
one set of measurements
between 0700 ¡V 1900 hours on normal weekdays;
(b)
one set of measurements
between 1900 ¡V 2300 hours;
(c)
one set of measurements
between 2300 ¡V 0700 hours; and
(d)
one set of measurements
between 0700 ¡V 1900 hours on holidays
During the reporting period,
the construction noise monitoring followed the scheme (a). The time and
duration of measurement are shown in the Appendix F.
The data for noise monitoring is
presented in Appendix F.
For M1, the results show that
during the reporting period, the noise level is on average 66.3 dB(A) which is
below the noise limit level 70 dB(A).
For M2, the results show that
during the reporting period, the noise level is on average 65.1 dB(A) which is
below the noise limit level 70 dB(A).
For M3, the results show that
during the reporting period, the noise level is on average 75.7 dB(A) which
exceeds the targeted noise limit level 70 dB(A). The new Exceedance Level is
now awaiting agreement with the EPD.
For M4, the results show that
during the reporting period, the noise level is on average 67.8 dB(A), which is
below the noise limit level 75 dB(A).
The major noise sources during
the reporting period include road construction at Ap Lei Chau Drive (Downhill
Site), shotcreting work on the slope area near Ap Lei Chau Bridge Road,
mini-piling work along Ap Lei Chau Bridge Road. Traffic also contributed to the
noise.
The
weather conditions were mainly sunny and did not affect the environmental
monitoring works during the reporting period. The weather conditions during the period are shown in the
Appendix H.
Other noise source included the noise from the
piling works at the site of Architectural Services Department inside the
monitoring station M3, the True Light College.
The
graphical plots of trends of monitored parameters at four monitoring stations
are shown in Appendix J.
4.1.1 Noise
During the reporting period, the
measured noise levels were below the noise limit level at the monitoring
stations M1, M2 and M4.
Based on the baseline noise monitoring results,
heavy traffic along Lei Tung Estate Road mainly contributes to the background
noise levels recorded in the vicinity of M3. As such, a new exceedance level,
which incorporates the baseline noise level into the limit level, is proposed
by ET according to the EM & A Manual Cl. 3.7. ET is now in liaison with and
is seeking approval from the EPD concerning the new Exceedance Level.
No written or verbal
complaints were received during the reporting period.
The following table shows
the summary for all the complaints received since the commencement of the
Contract.
|
TOTAL NO. OF COMPLAINT |
NO. OF COMPLAINT RECEIVED WITHIN REPORTING PERIOD |
NO. OF COMPLAINT THAT IS STILL UNDER INVESTIGATION |
NO. OF CLOSED COMPLAINT |
|
1 |
0 |
0 |
1 |
The statistics for environmental complaint in October
and the cumulative statistics for the environmental complaint since the
commencement of the construction works are shown in Appendix I.
No
mitigation measures were considered to be necessary as mentioned in Section
4.1.
No notifications of summons or
successful prosecutions were received by the Contractor regarding the
non-compliance of the environmental performance of the construction site during
the reporting period.
The non-compliance recorded at M3 is
both due to the noisy background noise generated from the heavy traffic on Lei
Tung Estate Road and the construction noise. Traffic noise dominates the noise
contribution although construction noise is considered to have a small
contribution on the recorded overall noise levels at M3.
Weekly site
inspections were conducted by the ET and the major findings during the
reporting period are summarized as follows:
¡P
Sand heap
was not properly covered;
¡P
Spread of
dust and particulate were found during slope shotcreting;
¡P
Accumulation
of surface runoff generated by mini-pile work; and
¡P
Spread of
construction dust generated by mini-pile work
After the
Contractor had received the environmental protection instructions issued by the
Environmental Team Leader after each site environmental audit, the
corresponding actions were undertaken as follows:
¡P
Cover the
sand heap with tarpaulin when not in use;
¡P
Wet the
area for shotcreting by means of spraying water;
¡P
Treat
surface runoff through sedimentation tank prior to the discharging to
stormwater drain; and
¡P
Erection
of tarpaulin barrier to stop the spread of construction dust to the nearby
pedestrian footway
In the coming month,
the following activities will be undertaken.
¡P
Slope
Works
¡P
Road Works
¡P
Mini-Piling
Works
¡P
Temporary
Traffic Diversion
Potential
environmental impacts arising from the above construction works are mainly
associated with dust, noise and site runoff.
Nonetheless,
with the implementation of the following mitigation measures, potential impacts
to the surrounding sensitive receivers could be minimised.
Construction Dust
¡P
Regular
watering of unpaved areas and the dry topsoil.
¡P
Wet by
water spraying on any dusty materials before loading and unloading.
¡P
Cover or
shelter any stockpile of dusty materials with tarpaulin.
¡P
Investigate
other dust sources.
¡P
Prohibit
any open burning on site.
¡P
Maintain
onsite machinery and vehicles regularly.
¡P
Switch off
vehicles and equipments while not in use.
¡P
Erection
of tarpaulin barrier to stop the spread of construction dust generated during
mini-pile work
Construction Noise
¡P
Carry out
good site practice.
¡P
Use
quieter plant.
¡P
Adopt
quiet working methods.
¡P
Enclose certain
type of power mechanical equipment such as generators and compressors.
¡P
Shut down
the machines and plant or throttle them down to a minimum when they are in
intermittent use between work periods.
¡P
Put the
noisy equipment away from nearby NSRs as far as possible.
¡P
Shift the
working hours as the last resort.
Construction Site Runoff
¡P
Direct the
site runoff to the desilting facilities.
¡P
Desilt the
site runoff before discharging it into the stormwater system.
¡P
Avoid
direct discharge of wastewater into stormwater drainage system.
Attention
should be given to the potential silty effluent resulting from the minipile
works (future works) for the footbridge foundation at Ap Lei Chau Bridge Road
to ensure it is treated as mentioned above before being discharged.
The Contractor should clean out any
sediments or debris which block the stormwater U-channels within the site area.
The Contractor should also remove any rubbish within the site area.
The Contractor should exert himself to
eliminate the presence of accumulation of stagnant water to avoid the breeding
of mosquitoes and the spread of dengue fever.
6.2.1 General Refuse
General refuse may be generated
by site workers. Bins shall be provided for containment prior to disposal of
such waste. The Contractor should avoid the accumulation of waste materials or
rubbish on site.
If there is any chemical waste or oil generated by
the site, they should be properly treated and disposed of as chemical waste. If
applicable, the Contractor should register as a chemical waste producer under
the registration of the Department of Environmental Protection.
Environmental awareness
shall be encouraged in office so as to reduce volume of office waste.
The accumulation of
construction waste materials should be avoided. Segregation of waste and
regular removal of waste materials on site are encouraged.
6.2.2 Liquid Waste Management
The accumulation of
stagnant water within the construction site should be avoided to eliminate
breeding grounds of mosquitoes.
To achieve this, the
Contractor should identify potential stagnant areas on the Site, provide
personnel to inspect the Site and take necessary rectification action such as
sweeping away the stagnant water to ensure no mosquitoes can breed.
To control the silty water,
the Contractor should provide sandbags/ bunds to
direct site surface runoff to the desilting facilities such as sedimentation
tanks. The desilting facilities should be
properly operated and maintained. To avoid the breeding of mosquitoes and other
insects, the sedimentation tank should not become a pool of stagnant water.
Care should also be taken to ensure the capacity of the desilting facilities is
sufficient to handle the discharge and to avoid overflow of the silty water.
The Contractor should
identify the sources of wastewater generated from the site area. The produced
wastewater should be collected and treated prior to disposal.










Monitoring
Point: M1 (Reference no. 10) Ap Lei Chau Baptist Kindergarten

Monitoring
Point: M2 (Reference no. 12) The Harbour Mission Church and Yan Oi Kindergarten

Monitoring Point: M3 (Reference no. 17) The Hong
Kong True Light College

Monitoring Point: M4 (Reference no. 20)
Shan On House
|
Contract
No. HY/2002/08 |
||||||||||||
|
Footbridge
and Improvements to Ap Lei Chau Bridge Road |
||||||||||||
|
and Ap Lei Chau Drive |
||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Monitoring Location: M1 Ap Lei Chau Baptist
Kindergarten (Ref.no.10) |
|
|
|
|
||||||||
|
Time Period: 07:00-19:00 |
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Start |
Duration
(min) |
Measurement
Results |
|||||||||
|
Date |
Time |
L90
(dB(A)) |
L10
(dB(A)) |
Leq(dB(A))
(5 mins) |
Leq(dB(A))
(30 mins) |
|||||||
|
02/10/03 |
10:35 |
30 |
63.7 |
67.8 |
66.2 |
65.8 |
65.9 |
66.0 |
66.2 |
66.3 |
66.1 |
|
|
08/10/03 |
11:05 |
30 |
63.7 |
67.5 |
65.9 |
66.2 |
65.8 |
65.6 |
66.1 |
66.4 |
66.0 |
|
|
16/10/03 |
13:35 |
30 |
63.4 |
66.9 |
65.6 |
65.5 |
65.6 |
65.4 |
65.8 |
65.4 |
65.6 |
|
|
22/10/03 |
10:25 |
30 |
64.4 |
70.3 |
65.8 |
70.3 |
71.2 |
69.8 |
66.1 |
69.3 |
68.8 |
|
|
30/10/03 |
13:25 |
30 |
63.9 |
66.9 |
65.8 |
64.7 |
64.6 |
64.6 |
66.1 |
64.5 |
65.1 |
|
|
Contract
No. HY/2002/08 |
||||||||||||
|
Footbridge
and Improvements to Ap Lei Chau Bridge Road |
||||||||||||
|
and Ap Lei Chau Drive |
||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Monitoring Location: M2 The Harbour Mission
Church & Yan Oi Kindergarten (Ref. no. 12) |
|
|
|
|
||||||||
|
Time Period: 07:00-19:00 |
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Start |
Duration
(min) |
Measurement
Results |
|||||||||
|
Date |
Time |
L90
(dB(A)) |
L10
(dB(A)) |
Leq(dB(A))
(5 mins) |
Leq(dB(A))
(30 mins) |
|||||||
|
02/10/03 |
11:14 |
30 |
61.7 |
67.0 |
64.3 |
64.3 |
64.5 |
64.6 |
64.9 |
64.5 |
64.5 |
|
|
08/10/03 |
13:45 |
30 |
62.1 |
67.1 |
64.5 |
64.5 |
64.8 |
64.6 |
65.1 |
65.2 |
64.8 |
|
|
16/10/03 |
14:23 |
30 |
62.1 |
66.8 |
64.7 |
64.6 |
64.5 |
64.6 |
64.8 |
64.7 |
64.7 |
|
|
22/10/03 |
11:18 |
30 |
63.6 |
69.9 |
65.3 |
65.8 |
68.4 |
69.0 |
64.8 |
66.2 |
66.6 |
|
|
30/10/03 |
14:05 |
30 |
62.8 |
68.3 |
64.2 |
65.5 |
64.5 |
65.3 |
65.5 |
65.5 |
65.1 |
|
|
Contract
No. HY/2002/08 |
||||||||||||
|
Footbridge
and Improvements to Ap Lei Chau Bridge Road |
||||||||||||
|
and Ap Lei Chau Drive |
||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Monitoring Location: M3 The Hong Kong True Light
College (Ref.no.17) |
|
|
|
|
||||||||
|
Time Period: 07:00-19:00 |
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Start |
Duration
(min) |
Measurement
Results |
|||||||||
|
Date |
Time |
L90
(dB(A)) |
L10
(dB(A)) |
Leq(dB(A))
(5 mins) |
Leq(dB(A))
(30 mins) |
|||||||
|
02/10/03 |
14:15 |
30 |
69.8 |
78.6 |
75.4 |
75.1 |
75.2 |
74.8 |
75.3 |
75.6 |
75.2 |
|
|
08/10/03 |
14:30 |
30 |
70.7 |
79.4 |
75.8 |
76.0 |
75.9 |
75.8 |
75.9 |
76.2 |
75.9 |
|
|
16/10/03 |
15:05 |
30 |
71.1 |
79.6 |
76.1 |
76.0 |
76.1 |
76.3 |
75.9 |
76.0 |
76.1 |
|
|
22/10/03 |
14:32 |
30 |
70.8 |
79.0 |
75.6 |
75.6 |
75.7 |
76.1 |
75.9 |
76.1 |
75.8 |
|
|
30/10/03 |
14:50 |
30 |
70.4 |
78.6 |
75.8 |
75.5 |
75.1 |
75.6 |
74.8 |
75.2 |
75.3 |
|
|
Contract
No. HY/2002/08 |
||||||||||||
|
Footbridge
and Improvements to Ap Lei Chau Bridge Road |
||||||||||||
|
and Ap Lei Chau Drive |
||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Monitoring Location: M4 Shan On House (Ref.no.20) |
|
|
|
|
||||||||
|
Time Period: 07:00-19:00 |
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Start |
Duration
(min) |
Measurement
Results |
|||||||||
|
Date |
Time |
L90
(dB(A)) |
L10
(dB(A)) |
Leq(dB(A))
(5 mins) |
Leq(dB(A))
(30 mins) |
|||||||
|
02/10/03 |
15:03 |
30 |
65.8 |
69.0 |
68.0 |
67.2 |
67.4 |
68.1 |
67.4 |
68.0 |
67.7 |
|
|
08/10/03 |
15:26 |
30 |
66.0 |
69.9 |
68.3 |
68.1 |
68.1 |
68.0 |
67.9 |
67.9 |
68.1 |
|
|
16/10/03 |
15:48 |
30 |
66.2 |
70.3 |
68.5 |
68.4 |
68.4 |
68.9 |
68.3 |
68.0 |
68.4 |
|
|
22/10/03 |
15:20 |
30 |
66.3 |
69.8 |
68.3 |
67.7 |
67.3 |
68.5 |
68.1 |
67.8 |
68.0 |
|
|
30/10/03 |
15:37 |
30 |
66.2 |
69.6 |
67.1 |
67.3 |
67.5 |
66.9 |
67.0 |
66.2 |
67.0 |
|



