PEAKO ENGINEERING CO., LTD

 

 

 


CONTRACT NO. HY/2002/08

Footbridge and Improvements to Ap Lei Chau

Bridge Road & Ap Lei Chau Drive

 

 

 


MONTHLY ENVIRONMENTAL MONITORING

 

& AUDIT REPORT

 

REPORT NO. 03

 

 

 

 

Document No. R/2647/004 Issue 1

 

 

 

 

August 2003

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Babtie Asia



CONTRACT NO. HY/2002/08

FOOTBRIDGE AND IMPROVEMENTS TO AP LEI CHAU BRIDGE ROAD

AND AP LEI CHAU DRIVE

 

MONTHLY ENVIRONMENTAL MONITORING & AUDIT REPORT

 

REPORT NO. 03

 

CONTENTS

 

EXECUTIVE SUMMARY

 

1.0             ENVIRONMENTAL STATUS

 

1.1     Background

1.2             Project Organization & Contact Details of Key Personnel

1.3             Construction Programme

1.4             Site Management Structure

1.5             Scope of Works

1.6             Works Undertaken during the Reporting Period with Illustrations

1.7             Project Area, Sensitive Receivers & Monitoring Locations

 

2.0             IMPLEMENTATION STATUS

 

2.1     Construction Phase

2.2     Advice on the Implementation Status of Environmental Protection & Pollution Control / Mitigation Measures

 

2.2.1  Construction Noise Mitigation Measures

 

3.0   MONITORING RESULTS

 

3.1     Graphical Plots of the Monitored Parameters

3.2     Major Activities During the Reporting Period

3.3     Noise Monitoring Methodology

3.4     Noise Monitoring Equipment

3.5     Calibration Details

3.6     Noise Parameters Monitored

3.7     Monitoring Locations

3.8     Monitoring Date, Time, Frequency and Duration

3.9     Noise Monitoring Results

3.10   Weather Conditions

3.11   Influencing Factors

3.12   Graphical Plots of Trends of Monitored Parameters

 

4.0     RECORD OF NON-COMPLIANCE OF THE ACTION AND LIMIT LEVELS, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND SUCCESSFUL PROSECUTIONS

 

4.1     Non-compliance of the Action and Limit Levels

 

4.1.1  Noise

 

4.2     Written Complaints and Verbal Complaints

4.3     Description of the Actions Taken

4.4     Notifications of Summons and Successful Prosecutions

4.5     Review of the Reasons for the Implications of Non-compliance & Complaints

 

5.0     SITE ENVIRONMENTAL AUDIT RESULTS

 

5.1             Site Inspection by Environmental Team (ET)

5.2             Site Inspection by Department of Environmental Protection

5.3     Corrective Actions by Contractor

 

6.0     OTHERS

 

6.1     Future Key Issues

6.2     Advice on the Solid and Liquid Waster Management Status

 

6.2.1  General Refuse

6.2.2  Liquid Waste Management

 

 

APPENDICES

 

Appendix A   Construction Programme

 

Appendix B   Site Organization Chart

 

Appendix C   Record Photos for Construction Activities in July 2003

 

Appendix D   The Project Area, Environmental Sensitive Receivers and the Locations of the Monitoring Stations

 

Appendix E   Calibration Certificates for Sound Level Meter

 

Appendix F   Data of Noise Monitoring

 

Appendix G   Graphical Representation of Construction Noise Monitoring Data

 

Appendix H   Weather Conditions & Major Activities during the Monitoring Period

 

Appendix I    Action & Limit Levels

 

Appendix J   Graphical Plots of Trends of Monitored Parameters

 

Appendix K   Construction Noise Monitoring and Site Audit Schedules

 

Appendix L   Cumulative Statistics on Environmental Complaints

 


EXECUTIVE SUMMARY

 

This is the third EM & A Report for the project of Footbridge and Improvements to Ap Lei Chau Bridge Road & Ap Lei Chau Drive.

 

This report mainly presents the EM & A works undertaken for the above project from 1 July 2003 to 31 July 2003 in accordance with the EM & A Manual and the Environmental Permit (EP 130/2002) under the Appendix H of the Particular Specification.

 

Breach of AL Levels

 

Leq (30min) noise level measurement was performed at four monitoring points namely M1, M2, M3 and M4. M1 is for the Ap Lei Chau Baptist Kindergarten (NSR Ref. no.10). M2 is for the Harbour Mission Church and Yan Oi Kindergarten (NSR Ref. no. 12). M3 is for the Hong Kong True Light College (NSR Ref. no. 17). M4 is for the Shan On House (NSR Ref. no. 20). Since the sensitive receivers on M1, M2 and M3 are for educational uses, the noise limit level is 70 dB(A) during normal school hours and 65 dB(A) during examination period. For the sensitive receiver on M4, the noise limit level is 75 dB(A) as it is a domestic premise.

 

The construction noise monitoring was conducted on the 3rd, 8th, 15th(for M1), 17th (for M2, M3, M4), 22nd and 31st of July 2003. All the measured noise levels at the three monitoring stations (M1, M2 and M4) were below the noise limit level. The measured noise levels at the monitoring station M3 were always higher than the targeted limit level. Since the engineering works at that concerned vicinity has not yet commenced, the noise is considered to be due to traffic generated from heavy goods vehicles such as double deck buses on Lei Tung Estate Road and due to the piling works from the ArchSD site inside the Hong Kong True Light College. It was agreed with the IEC that given that there are no project works in the vicinity of this sensitive receiver, no notification of noise limit exceedance were required to be issued for the exceedances recorded during this reporting period and no mitigation measures were required to be undertaken. The noise levels at this monitoring station will, however, be closely monitored when the construction works commence.

 

Complaint log & Others

 

No verbal or written complaints were received during the reporting period. No notifications of summons, no successful prosecutions were received during the reporting period.

 

Future Key Issues

 

Adverse influence on both air quality and noise level is anticipated from future construction activities. The Contractor should carry out good site practice to minimise the potential air pollution and noise pollution.

 

Since the rainy season is coming, the Contractor should exert himself to eliminate the presence of accumulation of stagnant water to avoid the breeding of mosquitoes and the spread of dengue fever.

 

To improve the hygiene condition of the site, the Contractor should provide rubbish bin where necessary and remove the rubbish, if any, within the site area.


1.0     ENVIRONMENTAL STATUS

 

1.1     Background

 

Peako Engineering Co. Ltd was commissioned by the Highways Departments to execute the Project “Footbridge and Improvements to Ap Lei Chau Bridge Road and Ap Lei Chau Drive”.

 

Babtie Asia Ltd was employed by the Contractor to act as the Environmental Team for this project. The Independent Environmental Checker is BMT Asia Pacific Limited.

 

The purpose of this report is to document the Environmental Monitoring & Audit (EM & A) works in the period between 1 July 2003 and 31 July 2003.

 

1.2     Project Organization & Contact Details of Key Personnel

 

Titles, names and contact telephone numbers of the key personnel of the captioned project are tabulated below:

 

Title

Name

Contact Number

Engineer’s Representative

(Highways Department)

Mr. W. M. Chan

2231 5722

EPD

Mr. Elvis Au

2835 1964

Project Director

(Contractor)

Mr. Ronnie Lo

9144 8398

Project Manager

(Contractor)

Mr. Steve C L Liu

9551 1401

Site Agent

(Contractor)

Mr. C. P. Lam

8206 8280

Environmental Team Leader

(Babtie Asia Limited)

Mr. Mark Cheung

2880 9788

Independent

Environmental Checker

(BMT Asia Pacific Limited)

Ms. Lyn Ip

2241 9812

 


The project organization and lines of communication with respect to the environmental monitoring works is shown below.

 

 


1.3     Construction Programme

 

The whole project will involve four key construction stages:

 

·                     footbridge construction;

·                     retaining wall construction;

·                     road construction; and

·                     drainage works

 

The overall construction period will be about 20 months. Night-time works are not expected during the construction phase of the Project.

 

The latest construction programme is attached in Appendix A. This construction programme is subject to continuous refinement.

 

1.4     Site Management Structure

 

The site organization chart is shown as Appendix B.

 

1.5     Scope of Works

 

The works for this project are divided into five major items

 

Item 1 –       Junction improvements to J/O Ap Lei Chau Bridge Road / Ap Lei Chau Drive, Ap Lei Chau Drive / Ap Lei Chau Praya Road, and widening of Ap Lei Chau Drive.

 

Item 2 –       Construction / modification of the footpaths and central reserves at Ap Lei Chau Bridge Road, Ap Lei Chau Drive, and Lei Tung Estate Road.

 

Item 3 –       Construction / modification of the retaining walls at Ap Lei Chau Bridge Road for the construction of a staircase, a ramp and an elevated footpath.

 

Item 4 –       Construction of a footbridge at Ap Lei Chau Bridge Road.

 

Item 5 –       Ancillary works including slope works, landscaping works and drainage works.

 

1.6     Works undertaken during the reporting period with illustrations

 

The works undertaken in July 2003 were as follows:

 

·                     Concreting for Mass Retaining Wall MW 4

·                     Construction of 2.0m Elevated Footway Deck

·                     Excavation of Road Surface Hard Materials

·                     Tree Felling Works along Ap Lei Chau Bridge Road

at the proposed cut slope area

·                     Tree Transplanting Works

·                     Temporary Concrete Pavement for TTA Implementation

 

The photos showing the above works are shown in Appendix C.

 

1.7     Project Area, Sensitive Receivers & Monitoring Locations

 

The drawings showing the project area, noise sensitive receivers (NSRs) and the locations of the monitoring stations are shown in Appendix D.

 

The construction noise monitoring stations are M1, M2, M3 and M4.

 

M1 is for the Ap Lei Chau Baptist Kindergarten (NSR Ref. no.10). M2 is for the Harbour Mission Church and Yan Oi Kindergarten (NSR Ref. no. 12). M3 is for the Hong Kong True Light College (NSR Ref. no. 17). M4 is for the Shan On House (NSR Ref. no. 20).

 

It is noted that the locations of the monitoring stations are the same as those adopted in the Noise Baseline Monitoring.


2.0     IMPLEMENTATION STATUS

 

2.1     Construction Phase

 

Impacts on the nearby sensitive receivers were identified during various construction stages. Appropriate mitigation measures such as use of quiet plant, reducing percentage on time, avoidance of simultaneous noisy activities have been recommended to reduce the associated impacts.

 

According to the EIA report, the following should be implemented during the construction period.

 

Location

Reference Section

Recommended Environmental Protection Measures

Responsibility

 

Construction Noise Mitigation Measures

 

Various Locations and work sites within the project limit

Section 5.2.4 & 5.2.5 of EIA Report

Reduce the nuisance from Construction Noise

 

·         Adopt good site practice and proper site management, e.g. plant shall be well maintained and mobile plant shall be sited away from NSRs;

·         Use of quiet plant, such as dump truck, grader, breaker and excavator, and working methods;

·         Control the number of equipment operating concurrently;

·         Reduce the operating time of particular noisy plant on site, e.g. shutting down machines between work periods;

·         Monitor noise levels from particularly noisy activities; and if non-compliance with EIAO-TM standards is observed, Contractor shall reduce the number of operating plant or re-adjust working schedule to reduce the impact.

Highways Department

 

and

 

Contractor

 

 

 

 

Location

Reference Section

Recommended Environmental Protection Measures

Responsibility

 

Construction Dust Mitigation Measures

 

Various Locations and work sites within the project limit

Section 6.2.2 of EIA Report

Reduce the nuisance of Construction Dust

 

·         Follow the guidelines and regulatory requirements of Air Pollution Control (Open Burning) Regulation and Air Pollution Control (Construction Dust) Regulation;

·         Adopt appropriate environmental pollution control measures on-site, such as, apply water sprays, use clean impervious sheeting to cover dusty materials and set minimum practical height for dropping materials.

 

Highways Department

 

and

 

Contractor


2.2     Advice on the Implementation Status of Environmental Protection & Pollution Control / Mitigation Measures

 

2.2.1  Construction Noise Mitigation Measures

 

The Contractor should use silencers or mufflers on construction equipment such as pneumatic breaker and air compressor to avoid exceeding the noise limit and causing nuisance to the nearby sensitive receivers.

 

Regular maintenance of the construction plant is strongly encouraged to avoid black smoke and excessive noise production. The machines and plant should be shut down or throttled down to a minimum when they are in intermittent use.

 

The plant known to emit noise strongly in one direction should be orientated to direct noise away from nearby noise sensitive receivers. The mobile plants should be sited as far away from the noise sensitive receivers as possible.

 

It is important to control the simultaneous operation of the construction plant on site to avoid the potential noise limit exceedance and nuisance to the nearby sensitive receivers especially for those which are for educational purpose.

 


3.0     MONITORING RESULTS

 

3.1     Graphical Plots of the Monitored Parameters

 

The graphical presentations of the monitored parameters during the reporting period are shown in Appendix G.

 

3.2     Major Activities During the Reporting Period

 

Major activities during July 2003 include the following:

 

·                     Concreting for Mass Retaining Wall MW 4

·                     Construction of 2.0m Elevated Footway Deck

·                     Excavation of Road Surface Hard Materials

·                     Tree Felling Works along Ap Lei Chau Bridge Road

at the proposed cut slope area

·                     Tree Transplanting Works

·                     Temporary Concrete Pavement for TTA Implementation

 

3.3     Noise Monitoring Methodology

 

The construction noise monitoring was carried out by using a Sound Level Meter to ensure that exceedance in noise levels could be readily identified and timely action taken to reduce the noise levels within allowable limits.

 

The sound lever meter was mounted on a tripod at a height of 1.2m above the ground level. This was positioned at least 1m away from any nearby reflective surfaces. During the noise data collection, a portable wind speed meter is adopted to check the wind speed.

 

Noise monitoring would be cancelled in the presence of fog, rain and wind with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s.

 

At the end of the monitoring period, the Leq, L10 and L90 were recorded. The site conditions and noise sources were recorded on a standard record sheet.

 

3.4     Noise Monitoring Equipment

 

The approved integrating Sound Level Meter, Model No. NA-27, in compliance with the International Electrotechnical Commission Publication 651:1979 (Type 1) and 804:1985 (Type 1) specification as referred to in the Technical Memorandum issued under the Noise Control Ordinance (NCO), was used for construction noise measurement.

 

3.5     Calibration Details

 

The Sound Level Meter has recently been taken to a laboratory for calibration. The certificate is shown in Appendix E.

 

A sound level calibrator, Model No. NC-73, was used to calibrate the Sound Level Meter before and after the measurement on site. The certificate is shown in Appendix E

3.6     Noise Parameters Monitored

 

The construction noise levels were measured in terms of equivalent A-weighted sound pressure level (Leq) measured in decibels (dB).

 

Leq(30min) was used as the monitoring parameter for the time period between (0700 to 1900) hours on normal weekdays.

 

The two statistical sound levels LA10 and LA90, the level exceeded for 10 and 90 percent of the measurement time respectively, were also recorded as supplementary information for reference.

 

3.7     Monitoring Locations

 

The noise baseline monitoring was conducted at four noise sensitive receivers as stated below.

 

Monitoring Location

Noise Sensitive Receiver

Ref. No. in the EIA Report

M 1

 

Ap Lei Chau Baptist Kindergarten

10

M 2

The Harbour Mission Church and Yan Oi Kindergarten

12

M 3

 

The Hong Kong True Light College

17

M 4

 

Shan On House

20

 

All the monitoring points are at façade. Hence, no correction of data is required.

 

Locations of construction noise monitoring stations and photos are shown in Appendix D.

 

3.8     Monitoring Date, Time, Frequency and Duration

 

The monitoring frequency will depend on the scale of the construction activities. The following was adopted as an initial arrangement of measurement on the regular monitoring frequency for each station on a per week basis when noise generating activities are underway:

 

(a)               one set of measurements between 0700 – 1900 hours on normal weekdays;

(b)               one set of measurements between 1900 – 2300 hours;

(c)               one set of measurements between 2300 – 0700 hours; and

(d)               one set of measurements between 0700 – 1900 hours on holidays

 

During the reporting period, the construction noise monitoring followed the scheme (a). The time and duration of measurement are shown in the Appendix F. 

 

 

 

 

3.9     Noise Monitoring Results

 

The data for noise monitoring is presented in Appendix F.

 

For M1, the results show that during the reporting period, the noise level is in average 66.5 dB(A) which is below the noise limit level 70 dB(A).

 

For M2, the results show that during the reporting period, the noise level is in average 65.9 dB(A) which is below the noise limit level 70 dB(A).

 

For M3, the results show that during the reporting period, the noise level is in average 74.4 dB(A) which exceeds the noise limit level 70 dB(A). No construction works were undertaken in the vicinity of this sensitive receiver.

 

For M4, the results show that during the reporting period, the noise level is in average 65.9 dB(A), which is below the noise limit level 75 dB(A).

 

The major noise sources during the reporting period include the erection of formwork at retaining wall CF1, coring work for ground inspection at CF1 and demolition of existing divider and safety island. Traffic also contributed to the noise.

 

3.10   Weather Conditions

 

The weather conditions were mainly sunny and did not affect the environmental monitoring works during the reporting period.  The weather conditions during the period are shown in the Appendix H.

 

3.11   Influencing Factors

 

Other noise source included the noise from the piling works at the site of Architectural Services Department inside the monitoring station M3, the True Light College.

 

3.12   Graphical Plots of Trends of Monitored Parameters

 

The graphical plots of trends of monitored parameters at four monitoring stations are shown in Appendix J.


4.0     RECORD OF NON-COMPLIANCE OF THE ACTION AND LIMIT LEVELS, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND SUCCESSFUL PROSECUTIONS

 

4.1     Non-compliance of the Action and Limit Levels

 

4.1.1  Noise

 

During the reporting period, the measured noise levels were below the noise limit level at the monitoring stations M1, M2 and M4.

 

However, all the measured noise levels at the monitoring station M3, the Hong Kong True Light College, exceeded the limit level. Since the construction works at the concerned vicinity has not yet commenced, the noise was considered to be due to the traffic generated from heavy goods vehicles such as double deck buses on Lei Tung Estate Road and due to the piling works from the ArchSD site inside the Hong Kong True Light College. Further to discussions with the IEC, it was agreed that no notification of noise limit exceedance was required to be issued for the exceedances recorded during this reporting period and no mitigation measures were required to be undertaken. The noise levels at this monitoring station will, however, be closely monitored when the construction works commence.

 

4.2     Written Complaints and Verbal Complaints

 

No written or verbal complaints were received during the reporting period.

 

The following table shows the summary for all the complaints received since the commencement of the Contract.

 

TOTAL NO. OF COMPLAINT

NO. OF COMPLAINT RECEIVED WITHIN REPORTING PERIOD

NO. OF COMPLAINT THAT IS STILL UNDER INVESTIGATION

NO. OF CLOSED COMPLAINT

1

0

0

1

 

The statistics for environmental complaint in July and the cumulative statistic for the environmental complaint since the commencement of the construction works are shown in Appendix I.

 

4.3     Description of Actions taken

 

No mitigation measures were considered to be necessary as mentioned in Section 4.1.

 

4.4     Notifications of Summons and Successful Prosecutions

 

No notifications of summons or successful prosecutions were received by the Contractor regarding the non-compliance of the environmental performance of the construction site during the reporting period.

 

 

 

4.5     Review of the Reasons for and the Implications of Non-Compliance & Complaints

 

The non-compliance recorded at M3 is solely due to the noisy background noise generated from the heavy traffic on Lei Tung Estate Road.

 


5.0     SITE ENVIRONMENTAL AUDIT RESULTS

 

5.1     Site Inspection by Environmental Team (ET)

 

Weekly site inspections were conducted by the ET and the major findings during the reporting period are summarized as follows:

 

·            The load (in-situ soil) carried by the vehicle leaving the site was not properly covered; and

·            Stockpile not properly covered.

 

5.2     Site Inspection by Department of Environmental Protection

 

          On 22 July 2003, three EPD inspectors carried out a site meeting with the Contractor and the ET to get familiar with the latest site condition and the implementation of certain environmental protection measures.

 

After the meeting, they carried out a site inspection together with the ET. During the joint inspection, the EPD inspectors advised the followings:

 

·         A sedimentation tank at works area for desilting purpose should be provided where necessary; the ET will advise the necessity in due course;

 

·         The Contractor shall properly desilt effluent  before discharging it to stormwater drainage system;

 

·         The Contractor shall properly treat the chemical waste if any;

 

·         Movable noise barrier may be needed, depending on the construction method by the Contractor at later construction stage; and

 

·         The Contractor shall keep close contact with the NSRs especially those for educational use.

 

5.3     Corrective Actions by Contractor

 

After the Contractor received the environmental protection instructions issued by the Environmental Team Leader after each site environmental audit, the corresponding actions were undertaken as follows:

 

·            Cover the load by clean impervious sheeting such as tarpaulin to ensure that dusty materials do not leak from the vehicle; and

·            Cover the stockpiles with tarpaulin when not in use.

 

 

 

 

 


6.0     OTHERS

 

6.1     Future Key Issue

 

In the coming month, the following activities will be undertaken.

 

·                     Slope Preparation Works

·                     Tree Felling

·                     Hoarding Erection

·                     Drainage Construction

·                     Road Works

·                     Utilities Diversion

·                     Temporary Traffic Diversion

 

Potential environmental impacts arising from the above construction works are mainly associated with dust, noise and site runoff.

 

Nonetheless, with the implementation of the following mitigation measures, potential impacts to the surrounding sensitive receivers could be minimised.

 

Construction Dust

 

·                     Regular watering of unpaved areas and the dry topsoil.

·                     Wet by water spraying on any dusty materials before loading and unloading.

·                     Cover or shelter any stockpile of dusty materials with tarpaulin.

·                     Investigate other dust sources.

·                     Prohibit any open burning on site.

·                     Maintain onsite machinery and vehicles regularly.

·                     Switch off vehicles and equipments while not in use.

 

Construction Noise

 

·                     Carry out good site practice.

·                     Use quieter plant.

·                     Adopt quiet working methods.

·                     Enclose certain type of power mechanical equipment such as generators and compressors.

·                     Shut down the machines and plant that may be in intermittent use between work periods or throttled them down to a minimum.

·                     Put the noisy equipment away from nearby NSRs as far as possible.

·                     Shift the working hours as the last resort.

 

Construction Site Runoff

 

·                     Direct the site runoff to the desilting facilities.

·                     Desilt the site runoff before discharging it into the stormwater system.

·                     Avoid direct discharge of wastewater into stormwater drainage system.

 

Attention should be given to the potential silty effluent resulting from the minipile works (future works) for the footbridge foundation at Ap Lei Chau Bridge Road to ensure it is treated as mentioned above before being discharged.

 

Since the heavy rainstorm season is coming, the Contractor should clean the sediments, if any, which block the stormwater U-channels within the site area. The Contractor should also remove any rubbish within the site area.

 

The Contractor should exert himself to eliminate the presence of accumulation of stagnant water to avoid the breeding of mosquitoes and the spread of dengue fever.

 

6.2     Advice on the solid and liquid waste management status

 

6.2.1  General Refuse

 

General refuse may be generated by site workers. Bins shall be provided for containment prior to disposal of such waste. The Contractor should avoid the accumulation of waste materials or rubbish on site.

 

If there is any chemical waste or oil generated by the site, they should be properly treated and disposed of as chemical waste. If applicable, the Contractor should register as a chemical waste producer under the registration of the Department of Environmental Protection.

 

Environmental awareness shall be encouraged in office so as to reduce volume of office waste.

 

The accumulation of construction waste materials should be avoided. Segregation of waste and regular removal of waste materials on site are encouraged.

 

6.2.2  Liquid Waste Management

 

The accumulation of stagnant water within the construction site should be avoided to eliminate breeding grounds of mosquitoes.

 

To achieve this, the Contractor should identify potential stagnant areas on the Site and take necessary rectification action, provide personnel to inspect the Site and take appropriate action to ensure no mosquitoes can breed.

 

To control the silty water, the Contractor should provide sandbags/ bunds to direct site surface runoff to the desilting facilities such as sedimentation tanks. The desilting facilities should be properly operated and maintained. In the meantime, the sedimentation tank should not become a pool of stagnant water to avoid the breeding of mosquitoes and other insects. Care should also be taken to ensure the capacity of the desilting facilities is sufficient to handle the discharge and to avoid overflow of the silty water.

 

For the wastewater generated from the site area, the Contractor should identify the sources. The produced wastewater should be collected and treated prior to disposal.

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 



 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 



 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 




 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

<