PEAKO ENGINEERING CO., LTD
CONTRACT NO. HY/2002/08
Footbridge and Improvements to Ap Lei Chau
Bridge Road & Ap Lei Chau Drive
MONTHLY
ENVIRONMENTAL MONITORING
&
AUDIT REPORT
REPORT
NO. 02
Document
No. R/2647/003 Issue 1
July
2003

Babtie Asia

CONTRACT NO.
HY/2002/08
FOOTBRIDGE AND IMPROVEMENTS TO AP LEI CHAU BRIDGE ROAD
AND AP LEI CHAU DRIVE
MONTHLY ENVIRONMENTAL MONITORING & AUDIT REPORT
REPORT NO. 02
CONTENTS
EXECUTIVE SUMMARY
1.0
ENVIRONMENTAL STATUS
1.1 Background
1.2
Project
Organization & Contact Details of Key Personnel
1.5
Scope of
Works
1.6
Works
Undertaken during the Reporting Period with Illustrations
1.7
Project
Area, Sensitive Receivers & Monitoring Locations
2.0
IMPLEMENTATION STATUS
2.2 Advice
on the Implementation Status of Environmental Protection & Pollution
Control / Mitigation Measures
2.2.1 Construction Noise Mitigation Measures
3.0 MONITORING
RESULTS
3.1 Graphical Plots of the Monitored Parameters
3.2 Major Activities During the Reporting Period
3.3 Noise Monitoring Methodology
3.4 Noise Monitoring Equipment
3.6 Noise Parameters Monitored
3.8 Monitoring Date, Time, Frequency and Duration
3.10 Weather Conditions
3.11 Influencing Factors
3.12 Graphical Plots of Trends of Monitored Parameters
4.0 RECORD
OF NON-COMPLIANCE OF THE ACTION AND
LIMIT LEVELS, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND SUCCESSFUL PROSECUTIONS
4.1 Non-compliance
of the Action and Limit Levels
4.1.1 Noise
4.2 Written Complaints and Verbal Complaints
4.3 Description of the Actions Taken
4.4 Notifications of Summons and Successful Prosecutions
4.5 Review of the Reasons for the Implications of Non-compliance
& Complaints
5.0 SITE
ENVIRONMENTAL AUDIT RESULTS
5.1 Site Inspection by Environmental Team (ET)
5.2 Corrective Actions by Contractor
6.0 OTHERS
6.2 Advice
on the Solid and Liquid Waster Management Status
6.2.1 General Refuse
6.2.2 Liquid Waste Management
APPENDICES
Appendix A Construction Programme
Appendix B Site Organization Chart
Appendix C Record Photos for Construction Activities in June 2003
Appendix D The Project Area, Environmental Sensitive Receivers and the
Locations of the Monitoring Stations
Appendix E Calibration Certificates for Sound Level Meter
Appendix F Data of Noise Monitoring
Appendix G Graphical Representation of
Construction Noise Monitoring Data
Appendix H Weather Conditions & Major Activities during the Monitoring
Period
Appendix I Action & Limit Levels
Appendix J Graphical Plots of Trends of Monitored Parameters
Appendix K Construction Noise Monitoring and Site Audit Schedules
Appendix L Cumulative Statistics on Environmental Complaints
EXECUTIVE SUMMARY
This is the second EM & A Report for the project of
Footbridge and Improvements to Ap Lei Chau Bridge Road & Ap Lei Chau Drive.
This report mainly presents the EM & A works
undertaken for the above project from 1 June 2003 to 30 June 2003 in accordance
with the EM & A Manual and the Environmental Permit (EP 130/2002) under the
Appendix H of the Particular Specification.
Breach of AL Levels
Leq (30min) noise level measurement was
performed at four monitoring points namely M1, M2,
M3 and M4. M1 is for the Ap Lei Chau Baptist Kindergarten (NSR Ref. no.10). M2
is for the Harbour Mission Church and Yan Oi Kindergarten (NSR Ref. no. 12). M3
is for the Hong Kong True Light College (NSR Ref. no. 17). M4 is for the Shan
On House (NSR Ref. no. 20). Since the sensitive receivers on M1, M2 and M3 are
for educational uses, the noise limit level is 70 dB(A) during normal school
hours and 65 dB(A) during examination period. For the sensitive receiver on M4,
the noise limit level is 75 dB(A) as it is a domestic premise.
The
construction noise monitoring was conducted on the 2nd, 5th
,13th ,17th and 24th of June 2003. All the
measured noise levels at the three monitoring stations (M1, M2 and M4) were
below the noise limit level. The measured noise levels at the monitoring
station M3 were always higher than the targeted limit level. A notification of
noise limit exceedance was issued to the Contractor and copied to the IEC, ER
and the EPD. Since the engineering works at that concerned vicinity has not yet
commenced, the noise is solely due to traffic generated from heavy goods
vehicles such as double deck buses on Lei Tung Estate Road. It was then agreed
with the IEC that no mitigation measures were required to be undertaken. The
noise levels at this monitoring station will, however, be closely monitored
when the construction works commence.
Based
on the advice from the IEC, a corrected noise level (CNL) with the deduction of
the background noise will represent the noise levels generated as a direct
result of the construction works. When the CNL value exceeds the limit level
(70 dB(A) during normal teaching hours and 65 dB(A) during exam periods), the
Contractor should take actions according to the Event/ Action Plan as
stipulated in the EM & A Manual Table 3.8a.
Complaint log
No
verbal or written complaints were received during the reporting period.
Others
No notifications of summons,
no successful prosecutions were received during the reporting period.
Future Key Issues
Adverse influence on both air
quality and noise level is anticipated from future construction activities,
such as demolition works for the existing CF1 retaining wall by the breakers.
The Contractor should carry out good site practice to minimise the potential
air pollution and noise pollution.
Since
the summer season is coming, the Contractor should exert himself to eliminate
the presence of accumulation of stagnant water to avoid the breeding of
mosquitoes and the spread of dengue fever.
To improve the hygiene
condition of the site, the Contractor should remove the rubbish, if any, within
the site area.
Peako
Engineering Co. Ltd was commissioned by the Highways Departments to execute the
Project “Footbridge and Improvements to Ap Lei Chau Bridge Road and Ap Lei Chau
Drive”.
Babtie Asia
Ltd was employed by the Contractor to act as the Environmental Team for this
project. The Independent Environmental Checker is BMT Asia Pacific Limited.
The purpose
of this report is to document the Environmental Monitoring & Audit (EM
& A) works in the period between 1 June 2003 and 30 June 2003.
Titles, names and contact
telephone numbers of the key personnel of the captioned project are tabulated
below:
|
Title |
Name |
Contact Number |
|
Engineer’s Representative (Highways Department) |
Mr. W.
M. Chan |
2231
5722 |
|
EPD |
Mr.
Elvis Au |
2835
1964 |
|
Project Director (Contractor) |
Mr.
Ronnie Lo |
9144
8398 |
|
Project
Manager (Contractor) |
Mr. Steve C L Liu |
9551 1401 |
|
Site
Agent (Contractor) |
Mr. C.
P. Lam |
8206 8280 |
|
Environmental
Team Leader (Babtie
Asia Limited) |
Mr.
Mark Cheung |
2880
9788 |
|
Independent
Environmental
Checker (BMT
Asia Pacific Limited) |
Ms.
Lyn Ip |
2241 9812 |

The project organization and lines
of communication with respect to the environmental monitoring works is shown
below.
The whole
project will involve four key construction stages:
·
footbridge
construction;
·
retaining
wall construction;
·
road
construction; and
·
drainage
works
The overall
construction period will be about 20 months. Night-time works are not expected
during the construction phase of the Project.
The latest
construction programme is attached in Appendix A. This construction programme
is subject to continuous refinement.
The site organization chart is shown as
Appendix B.
The
works for this project are divided into five major items
Item 1 – Junction
improvements to J/O Ap Lei Chau Bridge Road / Ap Lei Chau Drive, Ap Lei Chau
Drive / Ap Lei Chau Praya Road, and widening of Ap Lei Chau Drive.
Item 2 – Construction
/ modification of the footpaths and central reserves at Ap Lei Chau Bridge
Road, Ap Lei Chau Drive, and Lei Tung Estate Road.
Item 3 – Construction
/ modification of the retaining walls at Ap Lei Chau Bridge Road for the
construction of a staircase, a ramp and an elevated footpath.
Item 4
– Construction
of a footbridge at Ap Lei Chau Bridge Road.
Item 5 – Ancillary
works including slope works, landscaping works and drainage works.
The
works undertaken in June 2003 were as follows:
·
Concreting
for Mass Retaining Wall MW 4
·
Backfilling
for Mass Retaining Wall MW 4
·
Demolition
for Counterfort Retaining Wall CF1 (Lower 1.2m portion)
·
Formwork
erection for CF 1 (Section D to Section E)
·
Works by
Utility undertaker (HEC) at Ap Lei Chau Drive
The
photos showing the above works are shown in Appendix C.
The drawings showing the project
area, noise sensitive receivers (NSRs) and the locations of the monitoring
stations are shown in Appendix D.
The construction noise
monitoring stations are M1, M2, M3 and M4.
M1 is for the Ap Lei Chau
Baptist Kindergarten (NSR Ref. no.10). M2 is for the Harbour Mission Church and
Yan Oi Kindergarten (NSR Ref. no. 12). M3 is for the Hong Kong True Light
College (NSR Ref. no. 17). M4 is for the Shan On House (NSR Ref. no. 20).
It is noted that the locations
of the monitoring stations are the same as those adopted in the Noise Baseline
Monitoring.
Impacts on the nearby sensitive receivers were
identified during various construction stages. Appropriate mitigation measures
such as use of quiet plant, reducing percentage on time, avoidance of
simultaneous noisy activities have been recommended to reduce the associated
impacts.
According to the EIA report, the following should
be implemented during the construction period.
|
Location
|
Reference
Section |
Recommended
Environmental Protection Measures |
Responsibility |
|
Construction Noise
Mitigation Measures |
|||
|
Various
Locations and work sites within the project limit |
Section
5.2.4 & 5.2.5 of EIA Report |
Reduce the nuisance from Construction Noise ·
Adopt good site practice and proper site
management, e.g. plant shall be well maintained and mobile plant shall be
sited away from NSRs; ·
Use of quiet plant, such as dump truck, grader,
breaker and excavator, and working methods; ·
Control the number of equipment operating
concurrently; ·
Reduce the operating time of particular noisy
plant on site, e.g. shutting down machines between work periods; ·
Monitor noise levels from particularly noisy
activities; and if non-compliance with EIAO-TM standards is observed,
Contractor shall reduce the number of operating plant or re-adjust working
schedule to reduce the impact. |
Highways Department and Contractor |
|
Location
|
Reference
Section |
Recommended
Environmental Protection Measures |
Responsibility |
|
Construction Dust
Mitigation Measures |
|||
|
Various
Locations and work sites within the project limit |
Section
6.2.2 of EIA Report |
Reduce the nuisance of Construction Dust ·
Follow the guidelines and regulatory requirements
of Air Pollution Control (Open Burning) Regulation and Air Pollution Control
(Construction Dust) Regulation; ·
Adopt appropriate environmental pollution control
measures on-site, such as, apply water sprays, use clean impervious sheeting
to cover dusty materials and set minimum practical height for dropping
materials. |
Highways Department and Contractor |
2.2.1 Construction Noise Mitigation Measures
The Contractor should use silencers or mufflers on
construction equipment such as pneumatic breaker and air compressor to avoid
exceeding the noise limit and causing nuisance to the nearby sensitive
receivers.
Regular maintenance of the construction plant is
strongly encouraged to avoid black smoke and excessive noise production. The
machines and plant should be shut down or throttled down to a minimum when they
are in intermittent use.
The plant known to emit noise strongly in one
direction should be orientated to direct noise away from nearby noise sensitive
receivers. The mobile plants should be sited as far away from the noise
sensitive receivers as possible.
It is important to control
the simultaneous operation of the construction plant on site to avoid the
potential noise limit exceedance and nuisance to the nearby sensitive receivers
especially for those which are for educational purpose.
The graphical presentations of the monitored parameters during the reporting period are shown in Appendix G.
Major
activities during June 2003 include the following:
·
Concreting
for Mass Retaining Wall MW 4
·
Backfilling
for Mass Retaining Wall MW 4
·
Demolition
for Counterfort Retaining Wall CF1 (Lower 1.2m portion)
·
Formwork
erection for CF 1 (Section D to Section E)
·
Works by
Utility undertaker (HEC) at Ap Lei Chau Drive
The construction noise monitoring was carried out
by using a Sound Level Meter to ensure that exceedance in noise levels could be
readily identified and timely action taken to reduce the noise levels within
allowable limits.
The sound lever meter was mounted on a tripod at a
height of 1.2m above the ground level. This was positioned at least 1m away
from any nearby reflective surfaces. During the noise data collection, a
portable wind speed meter is adopted to check the wind speed.
Noise monitoring would be cancelled in the presence
of fog, rain and wind with a steady speed exceeding 5 m/s, or wind with gusts
exceeding 10 m/s.
At the
end of the monitoring period, the Leq, L10 and L90
were recorded. The site conditions and noise sources were recorded on a
standard record sheet.
The
approved integrating Sound Level Meter, Model No. NA-27, in compliance with the
International Electrotechnical Commission Publication 651:1979 (Type 1) and
804:1985 (Type 1) specification as referred to in the Technical Memorandum
issued under the Noise Control Ordinance (NOC), was used for construction noise
measurement.
The Sound Level Meter has recently been taken to a
laboratory for calibration. The certificate is shown in Appendix E.
A sound level calibrator, Model
No. NC-73, was used to calibrate the Sound Level Meter before and after the
measurement on site. The certificate is shown in Appendix E
The construction noise levels
were measured in terms of equivalent A-weighted sound pressure level (Leq)
measured in decibels (dB).
Leq(30min) was used
as the monitoring parameter for the time period between (0700 to 1900) hours on
normal weekdays.
The two statistical sound levels
LA10 and LA90, the level exceeded for 10 and 90 percent
of the measurement time respectively, were also recorded as supplementary
information for reference.
The noise baseline monitoring
was conducted at four noise sensitive receivers as stated below.
|
Monitoring
Location |
Noise
Sensitive Receiver |
Ref.
No. in the EIA Report |
|
M 1 |
Ap Lei
Chau Baptist Kindergarten |
10 |
|
M 2 |
The
Harbour Mission Church and Yan Oi Kindergarten |
12 |
|
M 3 |
The
Hong Kong True Light College |
17 |
|
M 4 |
Shan
On House |
20 |
All the monitoring points are at façade. Hence, no
correction of data is required.
Locations of construction noise monitoring stations
and photos are shown in Appendix D.
The
monitoring frequency will depend on the scale of the construction activities.
The following was adopted as an initial arrangement of measurement on the
regular monitoring frequency for each station on a per week basis when noise
generating activities are underway:
(a)
one set of measurements
between 0700 – 1900 hours on normal weekdays;
(b)
one set of measurements
between 1900 – 2300 hours;
(c)
one set of measurements
between 2300 – 0700 hours; and
(d)
one set of measurements
between 0700 – 1900 hours on holidays
During the
reporting period, the construction noise monitoring followed the scheme (a).
The time and duration of measurement are shown in the Appendix F.
The data for noise monitoring is
presented in Appendix F.
For M1, the results show that
during the reporting period, the noise level is on average 67.5 dB(A) which is
below the noise limit level 70 dB(A).
For M2, the results show that
during the reporting period, the noise level is on average 68.1 dB(A) which is
below the noise limit level 70 dB(A).
On 2 July 2003, one pneumatic
breaker was operating near M1 and M2 during the process of noise data
collection. During the 30-minute measurement, the breaker for concrete breaking
activities was operating nearly 80% of the measurement time.
For M3, the results show that
during the reporting period, the noise level is on average 73.5 dB(A) which
exceeds the noise limit level 70 dB(A). No construction works were undertaken
in the vicinity of this sensitive receiver.
For M4, the results show that
during the reporting period, the noise level is on average 66.7 dB(A), which is
below the noise limit level 75 dB(A).
No concrete breaking activities
were undertaken near the monitoring stations M3 and M4.
The major noise sources during
the reporting period include the operation of a pneumatic breaker for the demolition
and clearance works for Counterfort Retaining Wall CF1 and the excavation works
at MW 4, which were located at Ap Lei Chau Bridge Road near the junction and
the monitoring stations M1 and M2. Traffic also contributed to the noise.
The weather conditions were
mainly sunny, and did not affect the environmental monitoring works during the
reporting period. The weather
conditions during the period are shown in the Appendix H.
Other noise source included the
noise from the piling works at the site of Architectural Services Department
inside the monitoring station M3, the True Light College.
The graphical plots of trends of
monitored parameters at four monitoring stations are shown in Appendix J.
4.1.1 Noise
On 24 May 2003, the noise level
of M2 was found to be 72.7 dB(A) which exceeded the noise limit level during
school hours. The notification of noise limit exceedance was issued to the
Contractor. The investigation result shows that there was fixing works at the
external wall of the harbour Mission Church and Yan Oi kindergarten during the
whole daytime, while the Contractor was proceeding with the demolition of the
retaining wall CF1. At the very beginning of the demolition works in May 2003,
the Contractor had been confirmed by the principal of the Yan Oi kindergarten
that the normal school hour should be 8:00 am to 5:15 pm from Monday to Friday.
This was further verified by the ER. In addition, it was commonly agreed that
our works on Saturday would not affect the activities of the kindergarten. A
thorough coordination with the kindergarten had been conducted before the
Contractor actually proceeded with the engineering works.
Moreover, the demolition works
on Monday to Friday during May 2003 was carried out only after 5:15pm under the
Engineer’s verbal instruction. The noise monitoring was therefore conducted
mainly in the non-school hours, only when there were works activities in the
vicinity. In order to monitor the noise impact imposed on the sensitive receivers
for educational purpose, the monitoring schedule for this month was scheduled
to be undertaken during normal school hours.
During the reporting period, the
measured noise levels were below the noise limit level at the monitoring
stations M1, M2 and M4.
However, all the measured noise
levels at the monitoring station M3, the Hong Kong True Light College, exceeded
the limit level. A notification was issued to the Contractor and copied to the
IEC, ER and the EPD. An investigation was conducted. It was found that the
construction works at the concerned vicinity has not yet commenced. The noise
was solely due to the traffic generated from heavy goods vehicles such as
double deck buses on Lei Tung Estate Road. It was then agreed with the IEC that
no mitigation measures were required to be undertaken. The noise levels at this
monitoring station will, however, be closely monitored when the construction
works commence.
Based on the advice from the
IEC, a corrected noise level (CNL) with the deduction of the background noise
will represent the noise levels generated as a direct result of the
construction works. When the CNL value exceeds the limit level (70 dB(A) during
normal teaching hours and 65 dB(A) during exam periods), the Contractor should
take actions according to the Event/ Action Plan as stipulated in the EM &
A Manual Table 3.8a.
No
written or verbal complaints were received during the reporting period.
The
following table shows the summary for all the complaints received since the
commencement of the Contract.
|
TOTAL NO. OF COMPLAINT |
NO. OF COMPLAINT
RECEIVED WITHIN REPORTING PERIOD |
NO. OF COMPLAINT THAT IS
STILL UNDER INVESTIGATION |
NO. OF CLOSED COMPLAINT |
|
1 |
0 |
0 |
1 |
The statistics for environmental complaint in June
and the cumulative statistic for the environmental complaint since the
commencement of the construction works are shown in Appendix I.
No
mitigation measures were considered to be necessary as mentioned in Section
4.1.
No notifications of
summons or successful prosecutions were received by the Contractor regarding
the non-compliance of the environmental performance of the construction site
during the reporting period.
The non-compliance
recorded at M3 is solely due to the noisy background noise generated from the
heavy traffic on Lei Tung Estate Road.
Weekly site inspections
were conducted by the ET and the major findings during the reporting period are
summarized as follows:
·
Accumulation
of stagnant water; and
·
Inadequate
water supply or storage for dust suppression.
After the Contractor has
received the environmental protection instructions issued by the Environmental
Team Leader after each site environmental audit, the corresponding actions were
undertaken as follows:
·
Stagnant
water caused by rainy weather was discharged; and
·
Water
supply was installed at Ap Lei Chau Bridge Road.
In the coming month, the
following activities will be undertaken.
·
Construction
of Retaining Wall CF 1
·
Temporary
Traffic Diversion
·
Drainage
Construction
·
Road
Construction at Ap Lei Chau Drive
Potential environmental
impacts arising from the above construction works are mainly associated with
dust, noise and site runoff.
Nonetheless, with the
implementation of the following mitigation measures, potential impacts to the
surrounding sensitive receivers could be minimised.
Construction Dust
·
Regularly
watering of unpaved areas and the dry topsoil.
·
Cover the
stockpiles with tarpaulin.
·
Investigate
other dust sources.
·
Prohibit
any open burning on site.
·
Maintain
onsite machinery and vehicles regularly.
·
Switch off
vehicles and equipments while not in use.
Construction Noise
·
Carry out
good site practice.
·
Use
quieter plant.
·
Adopt
quiet working methods.
·
Enclose
certain type of power mechanical equipment such as generators and compressors.
·
Shut down
the machines and plant that may be in intermittent use between work periods or
throttled them down to a minimum.
·
Put the
noisy equipment away from nearby NSRs as far as possible.
·
Shift the
working hours as a last resort.
Construction Site Runoff
·
Direct the
site runoff to the desilting facilities.
·
Desilt the
site runoff before discharging it into the stormwater system.
·
Avoid
direct discharge of wastewater into stormwater drainage system.
Attention should be given
to the potential silty effluent resulting from the minipile works (future
works) for the footbridge foundation at Ap Lei Chau Bridge Road to ensure it is
treated as mentioned above before being discharged.
The location for carrying out the
demolition and construction works for the retaining wall CF1 and its subsequent
modification work is very near to the Ap Lei Chau Baptist Kindergarten (M1) and
The Harbour Mission Church and Yan Oi Kindergarten (M2). As such, the
Contractor should minimise the noise impact from the operation of the machines
and plant. Close monitoring on these two locations should be carried out to
avoid complaints.
Since the heavy rainstorm
season is coming, the Contractor should clean the sediments, if any, which
block the stormwater U-channels within the site area. The Contractor should
also remove any rubbish within the site area.
The Contractor should
exert himself to eliminate the presence of accumulation of stagnant water to
avoid the breeding of mosquitoes and the spread of dengue fever.
6.2.1 General Refuse
General refuse may be
generated by site workers. Bins shall be provided for containment prior to disposal
of such waste. The Contractor should avoid the accumulation of waste materials
or rubbish on site.
If there is any chemical waste or oil generated by
the site, they should be properly treated and disposed of as chemical waste. If
applicable, the Contractor should register as a chemical waste producer under
the registration of the Department of Environmental Protection.
Environmental awareness
shall be encouraged in office so as to reduce volume of office waste.
The accumulation of construction waste materials
should be avoided. Segregation of waste and regular removal of waste materials
on site are encouraged.
6.2.2 Liquid Waste Management
The accumulation of
stagnant water within the construction site should be avoided to eliminate
breeding grounds of mosquitoes.
To achieve this, the
Contractor should identify potential stagnant areas on the Site and take
necessary rectification action, provide personnel to inspect the Site and take
appropriate action to ensure no mosquitoes can breed.
To control the silty water,
the Contractor should provide sandbags/ bunds to
direct site surface runoff to the desilting facilities such as sedimentation
tanks. The desilting facilities should be
properly operated and maintained. In the meantime, the sedimentation tank
should not become a pool of stagnant water to avoid the breeding of mosquitoes
and other insects. Care should also be taken to ensure the capacity of the
desilting facilities is sufficient to handle the discharge and to avoid
overflow of the silty water.
For the wastewater
generated from the site area, the Contractor should identify the sources. The
produced wastewater should be collected and treated prior to disposal.









