Improvement to Castle Peak Road between Ka Loon Tsuen and Siu Lam
(updated as at 31.07.2007)
Project Title :
Improvement to Castle Peak Road between Ka Loon Tsuen and Siu Lam
Tender and Construction Consultant :
Ove Arup & Partners Hong Kong Limited
Contractor :
Gammon Construction Limited
Construction Commencement Date :
8 March 2004
Commissioning Date :
April 2007
(except minor outstanding works)
Approved Project Cost ($Million):
686.3
Project Objective :
The objective of the project is to widen and improve the section of the existing Castle Peak Road between Ka Loon Tsuen and Siu Lam to a dual two-lane carriageway.
Description :
The project includes :-
-
widening of a 1.1km section of CPR between Ka Loon Tsuen and Tai Lam Kok from a single three-lane carriageway to a dual two-lane carriageway;
-
construction of a 1.0-km section of new CPR between Tai Lam Kok and Siu Lam, including a 800-m long dual two-lane viaduct; and
-
reconstruction of the 1.2-km section of CPR between Tai Lam Kok and Siu Lam;and
- associated works on seawall construction, slope stabilisation, landscaping, street lighting and drainage.
Related Sites :
- Environmental Permit
(Application No. EP-01/171/2004/A) -
EIA Report
(Application No. EIA-054/2001)
| Current Contract No. | Contract Title |
|---|---|
| HY/2003/04 | Design and Build of Improvement to Castle Peak Road between Ka Loon Tsuen and Siu Lam (Works substantially completed except minor outstanding works) |