(a) 250m of dual 2-lane Approach Viaduct leading to
the proposed cross boundary bridge;
(b) 160m of dual
2-lane Approach Ramp of piled in-situ deck construction
for connecting (a) to existing roads in the Lok Ma
Chau Control Point;
(c) 120m of two-lane Overbridge
for passenger vehicles;
(d) diversion of the Ha
Wan Nullah; and
(e) Associated Works including at-grade
roads, drainage, sewers, watermains, slope
stabilization and protection works, traffic aids, street
lighting,
electrical and mechanical works, traffic control
and surveillance system works, fire services
main, irrigation
system, hard and soft landscaping, fire hydrants
and emergency crossing.