

CONTRACT NO. HY/98/22
SUPPLEMENTARY AGREEMENT NO. 3
ROAD WIDENING WORKS OF SALISBURY
ROAD
BETWEEN NATHAN ROAD AND CANTON ROAD
MONTHLY EM&A REPORT NO. 1
CONTENTS
1.1 Background
1.2 Project
Organisation and Management Structure for EM&A Works
1.3 Construction
Programme
1.4 Works
undertaken in March 2002
1.5
Project Works Area
2.0 SUMMARY
OF EM&A REQUIREMENTS
2.1 Air Quality
2.2 Noise
2.3
Environmental Mitigation
Measures
2.4
Environmental Requirements in
Contract Documents
3.0 IMPLEMENTATION
STATUS ¡V ADVICE ON THE IMPLEMENTATION OF ENVIRONMENTAL MITIGATION MEASURES
4.0 ENVIRONMENTAL
STATUS AND MONITORING RESULTS
4.1
Air Quality
4.2
Noise
4.3
Adverse effects on Air Quality
and Noise Level from Non-Construction Activities and/or Activities from other
Construction Sites
5.0 RECORD OF NON-COMPLIANCE, COMPLAINTS,
NOTIFICATIONS OF SUMMONS AND SUCCESSFUL PROSECUTIONS
5.1
Non-compliance
5.2
Complaints (Including Verbal
Complaints)
5.3
Notifications of Summons and
Successful Prosecutions
7.0 ADVICE
ON THE SOILD AND LIQUID WASTE MANAGEMENT STATUS
7.1
Excess Excavated Materials
7.2
Construction Waste
7.3
Demolition Waste
7.4
Chemical Waste
7.5
General Refuse
8.0 SUBMISSION OF SITE INSPECTION PROFORMA
8.1 Potential
Environmental Impact
8.2 Mitigation Measures
APPENDICES
Appendix A Project Organisation Chart and
Management Structure for EM&A Works
Appendix B Construction Programme
Appendix C Project Works Area
Appendix D Locations of Air Sensitive
Receivers
Appendix E Implementation Schedule of
Environmental Mitigation Measures
Appendix F Record Photos
Appendix G Site Inspection
Proforma for March 2002
Appendix H Standard Site
Audit Checklist
This is the first EM&A Report
for the project of Road Widening Works of Salisbury Road between Nathan Road
and Canton Road. The contract entitled ¡¥Contract No. HY/98/22, Supplementary Agreement
No. 3, Road Widening Works of Salisbury Road between Nathan Road and Canton
Road¡¦ was awarded to Downer Construction (Hong Kong) Limited in February 2002.
This report mainly presents the
EM&A works undertaken for the project from 1 March 2002 to 31 March 2002.
Air Quality
Site inspection was carried out
once per week by checking the adequacy of the mitigation measures implemented
by the Contractor with reference to the EM&A Manual.
No obvious air quality
deterioration was recorded during the reporting period.
Noise Level
No indication of noise exceedance
was observed during weekly site inspections for this reporting period.
Others
No non-compliance, no complaints,
no notifications of summons and successful prosecutions were received.
Future Key Issues
Future construction activities,
such as excavation, resurfacing, footpath construction, drainage works and
landscaping works should be closely monitored to ensure the effects on air quality
and noise level are minimised.
1.1 Background
Downer Construction (Hong Kong) Limited is the Contractor for the
Supplementary Agreement No. 3 (SA3) for the Contract No. HY/98/22 Road Widening
Works of Salisbury Road between Nathan Road and Canton Road. The major
activities during construction of SA3 includes widening of the existing
carriageways by providing an additional lane from Hong Kong Space Museum to
Hong Kong Cultural Centre. Other construction works include resurfacing,
central divider and footpath reconstruction, drainage works and landscaping
works.
The purpose of this report is to report the EM&A works in the period
between 1 March 2002 and 31 March 2002.
1.2 Project Organisation and Management Structure
for EM&A Works
An environmental team (ET)
has been established to investigate and audit the Contractor¡¦s equipment and
work methodologies, to monitor and to audit reports, and to provide
recommendations and improvements. An Independent Environmental Checker (IEC)
has been employed to review the EM&A works by the ET. The Engineer is
generally responsible for supervising the contractor¡¦s activities, reviewing
the EM&A works and mitigation measures. Section 1.4 of the EM&A Manual
can also be referred for the overall works.
The
project organization chart and management structure for EM&A works are
shown in Appendix A.
1.3 Construction
Programme
The latest construction
programme is included in Appendix B. The programme will be subject to continuous
refinement during the project period.
1.4 Works
undertaken in March 2002
The
major construction activities and works undertaken in March 2002 were as
follows:
¡P
Site clearance and hoarding
erection along southbound Salisbury Road from Hong Kong Space Museum to Hong
Kong Cultural Centre
¡P
Temporary bus-stop removal
¡P
Ducting diversion (CLP and
PCCW)
¡P
ATC and street lighting
drawpit/ ducting
¡P
Resurfacing works
¡P
Drainage works
¡P
Relocation of direction
signs
1.5 Project
Works Area
The
project works area is shown in Appendix C. The boundary of the works area to
the west of Nathan Road is also shown in Appendix C.
2.0 SUMMARY OF EM&A REQUIREMENTS
2.1 Air Quality
According to
Section 1.3 of the EM&A Manual, the captioned project involves minor road
widening works. Because of the short construction period (approximately 6 to 7
months), together with staged construction sequence of works which will limit
the extent of construction area at any one time. Therefore, air quality is
monitored by means of checking the adequacy of dust mitigation measures
implemented by the Contractor (Please refer to Section 2.1 of the EM&A
Manual or Section 2.3.1 of this report for dust mitigation measures). It is
anticipated that proper implementation of dust reduction measures will be
adequate to mitigate dust impacts and maintain Total Suspended Particulate
(TSP) concentration levels within those recommended under the Air Quality
Objectives (AQO) and no further air quality monitoring will be necessary.
All of the dust
monitoring locations identified in the EIA Study is located in the vicinity of
the proposed vehicular underpass (located at the Salisbury Road/Chatham Road
South junction), the monitoring works of which will be carried out as part of
the works east of Nathan Road by KCRC. Hence, the standard requirements of
collating Baseline Monitoring Results, calculation of Action and Limit Levels
etc. have been omitted from this report. These requirements will be fulfilled
under the EM&A for the works east of Nathan Road.
Should there be
any obvious air quality deterioration as a result of the construction works,
the ET will perform additional monitoring (for example, using air quality monitoring equipment) to
measure TSP concentration levels so as to ensure that any deteriorating air
quality can be readily detected and timely action is to be taken to rectify the
situation. Additional monitoring will be performed by the ET in the event of
complaints from the local residents.
2.1.1 Air Sensitive Receivers
According to Section 7.4 of the EIA
Report, Peninsula Hotel, YMCA Hotel, Space Museum, Museum of Art and Hong Kong
Cultural Centre are identified as air sensitive receivers. Their locations are
shown in Appendix D.
2.2 Noise
Though
requirements for noise monitoring has not been specified in the EM&A
Manual, during the course of site inspection carried out by the ET, the ET will
closely monitor construction noise. Should there be any obvious indication of
construction noise level exceedance observed by the ET during site inspections,
the ET will perform additional monitoring and will carry out noise monitoring
works to measure the exceedance of noise level, with reference to the Noise
Control Ordinance. Measurement of construction noise level will be carried out using
an Integrating Sound Level Meter with calibrator which complied with EPD's
requirements. Additional
monitoring will be performed by the ET in the event of complaints from the
local residents.
2.2.1 Noise Sensitive Receivers
According to Section 4.3 of the EIA
Report, the noise standards only apply to dwellings relying on opened windows
for ventilation. Since central air conditioning systems are provided for all
hotels which do not rely on openable windows for ventilation, these noise
sensitive receivers are less sensitive to noise impacts.
2.3 Environmental Mitigation Measures
2.3.1 Air Quality
Dust control and
mitigation measures to be implemented during the construction phase are listed
in Section 2.1 of the EM&A Manual. The Contractor should:
¡P
Use of regular watering to reduce dust emissions from exposed site
surfaces and unpaved roads, with complete coverage, particularly during dry
weather;
¡P
Use of frequent watering for
particularly dusty static construction areas and areas close to air quality
sensitive receivers;
¡P
Side enclosure and covering of any
aggregate or dusty material storage piles to reduce emissions. Where this is
not practicable owing to frequent usage, watering should be employed to
aggregate fines;
¡P
Tarpaulin covering of all dusty vehicle
loads transported to, from and between site locations;
¡P
Establishment and use of vehicle wheel
and body washing facilities at the exit points of the site, combined with
cleaning of public roads where necessary;
¡P
Imposition of speed controls for
vehicles and unpaved site roads;
¡P
Where feasible, routing of vehicles and
positioning of construction plant should be at maximum possible distance from
air quality sensitive receivers; and
¡P
Instigation of an environmental monitoring
and auditing program to monitor the construction process in order to enforce
controls and modify methods of work if dusty conditions arise.
According to
Section 1.3 of the EM&A Manual, it is anticipated that proper
implementation of dust reduction measures will be adequate to mitigate dust
impacts and maintain TSP concentration levels within those recommended under
the Air Quality Objectives (AQO), and no further air quality monitoring will be
necessary.
Site inspection
is carried out by the ET at least once per week according to Section 4.1 of the
EM&A Manual. During the course of site inspection, the ET will check if the
Contractor implements the aforementioned dust mitigation measures during
construction phase.
Violation of EM&A requirements and/or complaints
on air quality
Should the
Contractor does not implement the aforementioned dust mitigation measures
properly during construction phase and resulting in deterioration of air
quality, and/or complaints (including verbal complaints) are received from
local residents, the ET will perform TSP concentration level measurement.
¡P
Monitoring
methodology
The Total
Suspended Particulate (TSP) concentration levels are sampled by drawing air
through a piece of conditioned and pre-weighed filter paper inside the High
Volume Sampler at controlled flow rate. After sampling, the filter paper with
the retained particulate is further conditioned and weighed. The TSP level is
calculated from the ratio of the mass of particulate retained on the filter
paper to the total volume of air sampled.
¡P
Monitoring
equipment
High Volume
Sampler (Model no. GMW SA2310-105) will be used for TSP concentration levels
measurement. Its associated calibrator (Model no. Anderson G3357K S/N: F31/42J)
will be used for calibration.
¡P
Monitoring
parameters
1.
24-hour
TSP concentration level for every week
2.
3x1-hour
TSP concentration level for every six days
If TSP concentration levels exceed their
respective allowable limits, timely action will be taken to rectify the
situation.
2.3.2 Noise
During the
course of site inspection, the ET will closely monitor construction noise.
Construction noise level exceedance and/or complaints
on construction noise
Should there be
any obvious indication of construction noise level exceedance observed by the
ET during site inspections, and/or complaints (including verbal complaints) are
received from local residents, the ET will perform construction noise
measurement.
¡P
Monitoring
methodology
The construction
noise levels are measured in terms of the A-weighted equivalent continuous
sound pressure level (Leq). Leq (30 min) is taken as the
monitoring parameter for the time period between 0700-1900 hours on normal weekdays
during normal hours (0700-1900 Monday to Saturday excluding public holidays). Leq
(30 min) is monitored as 6 consecutive Leq (5 min) readings.
¡P
Monitoring
equipment
Integrating
Sound Level Meter (Model no. CESVA SC20-e) will be used for construction noise
level measurement. Its associated calibrator (Model no. CESVA CB-5) will be
used for calibration.
¡P
Monitoring
parameters
1.
Leq
(30 min) for the time period between 0700-1900 hours on normal weekdays
2.
L10
and L90 (for reference)
If construction noise levels exceed
their the allowable limits, timely action will be taken to rectify the
situation.
2.4 Environmental
Requirements in Contract Documents
The EPD's standard pollution control clauses have been
incorporated into contract documents and regular auditing by the ET and the IEC
to ensure mitigation measures are properly implemented by the Contractor, and
will be sufficient to relieve dust impacts.
3.0 IMPLEMENTATION
STATUS - Advice on the implementation of
environmental mitigation measures
Implementation Schedule of Environmental Mitigation
Measures is shown in Appendix E.
4.0 ENVIRONMNETAL STATUS AND MONITORING RESULTS
4.1 Air
Quality
As the mitigation measures implemented by the
Contractor during site inspections are adequate, no TSP level has to be
recorded. Please refer to photos in Appendix F for implementation of dust
reduction measures done by the Contractor.
Photos in
Appendix F show the environmental mitigation measures implemented by the
Contractor to control dust emissions during this reporting period.
Photo 1 shows
excavated materials to be transported to dumping site being covered with
tarpaulin covering, which can effectively reduce dust emissions during
transportation of dusty materials.
Photo 2 shows
removal of excavated materials from roadside, which can avoid dust emissions by
speedy vehicles.
Photo 3 shows screening of the construction site with
hoardings to reduce dust emissions during the construction phase. However, the
excavated site is not covered with tarpaulin. In order to minimise dust
emissions, the Contractor later covers the excavated site and dusty material
stockpiles with tarpaulin (Photo 4).
4.2 Noise
No obvious noise level exceedance was observed during
site inspections.
4.3 Adverse
effects on Air Quality and Noise Level from Non-construction Activities and/or
Activities from other Construction Sites
During the course of site inspection, no adverse
effects on air quality and noise level due to non-construction activities
and/or activities from other construction sites were observed.
5.0 RECORD
OF NON-COMPLIANCE, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND SUCCESSFUL
PROSECUTIONS
5.1 Non-compliance
5.1.1 Air Quality
No non-compliance was identified during site
inspections as the mitigation measures implemented by the Contractor during
site inspections are adequate.
5.1.2 Noise
No non-compliance in construction noise level was
observed during site inspections.
5.2 Complaints
and Verbal Complaints
No
complaint and verbal complaint were received in the reporting month.
5.3 Notifications
of Summons and Successful Prosecutions
No notifications
of summons or successful prosecutions were received in the reporting
month.
The proposed
construction works to be carried out in the next reporting period (April 2002)
are as follows:
¡P
ATC and street lighting drawpit/ ducting
¡P
Drainage works
¡P
Resurfacing and reconstruction works along southboard Salisbury Road
¡P
Street lighting diversion at footpath area
¡P
Reinstatement of pavement area
¡P
Road signage at footpath area
Some of them may
have potential environmental impact and will require mitigation measures, and
such activities will be monitored closely during future site inspections.
7.0 ADVICE
ON THE SOLID AND LIQUID WASTE MANAGEMENT STATUS
The waste management plan
has been submitted in this reporting period. The Contractor has carried out
construction works in accordance with Waste Management Plan.
7.1 Excess
Excavated Materials
The Contractor stockpiles
excavated materials which will be reused for landscaping and backfilling
temporarily on site. These excavated materials are covered with tarpaulin
(please refer to Photo 4 of Appendix F for reference).
Excavated materials which
cannot be reused for backfilling were transported to either Tseung Kwan O
public filling area or Tolo Harbour Reclamation Area, according to the Waste
Management Plan. Such materials were covered with tarpaulin, which could effectively
reduce dust emissions during transportation (please refer to Photo 1 of
Appendix F for reference).
7.2 Construction
Waste
According to the Waste
Management Plan, the Contractor separated construction waste which could be reused
on site and recycled with those to be disposed of. This was carried out by
general workforce under supervision of Foremen and charge hands. For example,
timber (for formwork) was cleaned for reuse, steel was stored for reuse,
reinforcement was sorted into usable lengths for recycling or reuse on site.
7.3 Demolition
Waste
None of the demolition
waste generated in the captioned project will be reused, according to the Waste
Management Plan. Such waste is transported to either Tseung Kwan O public filling
area or Tolo Harbour Reclamation Area.
7.4 Chemical
Waste
No chemical waste is
generated in the captioned project.
7.5 General
Refuse
The Contractor deposited
aluminium cans, plastic bottles and glass bottles in separately labelled bins for
recycling and reuse.
The
Contractor reduced office wastes through recycling of paper. Signs encouraging
environmental awareness, such as reducing the number of photocopies to a
minimum and using both sides of papers, etc., were put on in the Contractor¡¦s
site office.
8.0 SUBMISSION OF SITE INSPECTION PROFORMA
Site
inspection proforma for March 2002 is attached in Appendix G. Locations of
deficiencies are shown on the site plan attached in Appendix G.
A
standard site audit checklist is attached in Appendix H.
Weather
condition during all site inspections carried out in March 2002 is fine. Wind
is minimal.
8.1 Potential
Environmental Impact
According
to the site inspection proforma for March 2002, the following deficiencies are
recorded:
1.
Site hoardings are erected
on only 3 sides of the site.
2.
Some heaps of excavated
materials are not covered.
If site
hoardings are not erected to screen all sides of the site, and heaps of
excavated materials are not covered, dust emission from the excavated area and
the excavated materials may have adverse influence on air quality.
8.2 Mitigation
Measures
In order
to mitigate the environmental impacts as described in Section 8.1, the
Contractor had been advised to erect site hoardings on all 4 sides of the site
so as to completely screen the site, and to cover heaps of excavated materials
with tarpaulin so as to reduce dust emissions.
APPENDIX A PROJECT ORGANISATION CHART AND MANAGEMENT
STRUCTRUAL FOR EM&A WORKS
|
|
|
Highways Department Contact Person: Mr. Simon C.H. Leung Telephone No.: 2707 7250 ¡P
Overall responsibility of the Project ¡P
Co-ordinate with EPD for decision making for any
non-compliance observed |
|
|
|
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Engineer¡¦s Representative (ER) Contract Person: Mr. Felix Chan Telephone No.: 2605 6262 ¡P
Supervise the Contractor¡¦s activities and ensure
that requirements in the EM&A Manual are fully complied with ¡P
Inform the Contractor when action is required to
reduce impacts ¡P
Review the EM&A works performed by the ET |
|
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Environmental Protection Department (EPD) (EM&A Section) Contact Person: Mr. Anthony Y.K. Ho Telephone No.: 2835 1871 ¡P
Regulatory body ¡P
EM&A approval |
|
|
The Contractor Contact Person: Mr. M.W. Suen (Site Agent) Telephone No.: 9202 9341 ¡P
Employ the ET to undertake monitoring, and
reporting of EM&A ¡P
Provide assistance to the ET in carrying out
monitoring ¡P
Implement measures to reduce impact |
||
|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Independent Environmental Checker (IEC) Contact Person: Mr. Tim Cramp Telephone No.: 2893 1551 ¡P
Review the EM&A works performed by the ET ¡P
Audit monitoring activities and results ¡P
Review the EM&A reports submitted by the ET |
|
|
Environmental Team (ET) Contact Person: Mr. Mark K.T. Cheung Telephone No.: 2738 3803 ¡P
Monitor the various environmental parameters as
required in the EM&A Manual ¡P
Carry out site inspections to investigate and audit
the Contractor¡¦s site practices, equipment and work methodologies with
respect to pollution control and environmental mitigation and anticipate
environmental issues for proactive action before problems arise ¡P
Audit and prepare audit reports on the environmental
monitoring data and the site environmental conditions |
||
|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
|
|
|
|
|
Supplementary
Agreement No. 3
Road
Widening Works of Salisbury Road
between
Nathan Road and Canton Road

Management
Structure for EM&A Works
Road
Widening Woks of Salisbury Road
Between
Nathan Road and Canton Road
APPENDIX B CONSTRUCTION PROGRAMME







APPENDIX D LOCATIONS OF AIR SENSITIVE RECEIVRS

APPENDIX E IMPLEMENTATION SCHEDULE OF
ENVIRONMENTAL MITIGATION MEASURES
The
schedule of implementation of the recommended mitigation measures for various
environmental aspects are presented in Tables E1 and E4 for different
environmental aspects
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures/Timing of completion of Measures |
Implementation
Dept/agent |
Implementation
Stage |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||
|
Section
3.5 |
Section
2.1 |
Established
standards and guidelines with EPD¡¦s recommended pollution control clauses
should be incorporated in the contract documents |
During
Construction Phase within the site area |
Contractor |
Ö |
Ö |
|
|
|
Dust
reduction measures while carrying out construction works in accordance with
the Air Pollution Control (Construction Dust) Regulation to minimise the dust
emission from the construction site |
Ö |
Ö |
|
TM
on EIA Process, APCO, Air Pollution Control (Construction Dust) Regulation |
||||
Notes:
1.
Des = Design, C = Construction, Op = Operation
2.
EIA Ref = Section number reference in EIA for
Salisbury Road Underpass and Associated Road Improvement Works including Middle
Road Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
Table E2 Summary
of Proposed Mitigation Measures for Construction Waste Management
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures/Timing of completion of Measures |
Implementation
Dept/agent |
Implementation
Stage |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||
|
Section
6.3 |
Section
3.1 |
On-site
separation of both municipal solid waste and C&D waste should be
conducted as far as possible.
Construction waste should be sorted on-site into construction &
demolition waste and public fill fraction for re-use and recycling as far as
practical |
During
Construction Phase within the site area |
Contractor |
Ö |
Ö |
Ö |
TM
on EIA Process, WDO |
|
Waste
management measures would be proposed in accordance with the Criteria for Evaluating
Waste Management Implications stipulated in Annex 7 of the TM EIAO and follow
the Guidelines for Assessment of Waste Management Implications stated in
Annex 15 of the TM EIAO as appropriate |
||||||||
|
Standard
C&D materials management clause should be included in the construction
contact |
||||||||
Notes:
1.
Des = Design, C = Construction, Op = Operation
2.
EIA Ref = Section number reference in EIA for
Salisbury Road Underpass and Associated Road Improvement Works including Middle
Road Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
Table E3 Summary
of Proposed Mitigation Measures for Visual Impact
|
EIA Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures |
Funding
Dept/agent |
Implementation
Dept/agent |
Maintenance
Agent |
Implementation
Stages |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||||
|
Section
8.7 (Temporary Mitigation Measures |
N/A |
Screening
of site works by hoardings |
In
place at the commencement and for the duration of the Construction Phase with
the site area |
HyD |
Contractor |
Contractor
(During Construction Phase) |
Ö |
Ö |
|
|
|
Surface
treatment of site hoardings to enhance their visual interest and harmony with
surrounding landscape/townscape |
|
|
|
|||||||
|
Locating
temporary buildings (e.g. Site office) in least visually prominent locations |
Design Engineer/Contractor |
|
Ö |
|
||||||
|
Retention
of vegetation within the works site area where possible |
Landscape
Architect / Contractor |
Ö |
Ö |
|
||||||
|
Provision
of fences around all the low, circular raised planters to ensure that
materials and debris will not be dumped on tree roots |
Contractor |
|
Ö |
|
||||||
|
Footpaths
along south side of Salisbury Road will be replanted with heavy standard
trees where possible. The
proposed planning will also reprovide shading along the footpath temporarily
removed during the construction stage |
In
place by the completion of Construction Phase within the site area, to be
maintained for the duration of Operation Phase |
HyD |
Landscape
Architect/Contractor |
Contractor
(During construction phase) LCSD
(during operation phase) |
Ö |
|
Ö |
|
||
Notes:
1.
Des = Design, C = Construction, Op = Operation
2.
EIA Ref = Section number reference in EIA for
Salisbury Road Underpass and Associated Road Improvement Works including Middle
Road Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
Table E4 Summary
of Proposed Mitigation Measures for Landscape and Townscape Impacts
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures |
Funding
Dept/agent |
Implementation
Dept/agent |
Maintenance
Agent |
Implementation
Stages |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||||
|
Section
8.8 (Temporary Mitigation Measures |
N/A |
Re-routing
of pedestrian routes away from the work site where possible |
In
place at the commencement and for the duration of the Construction Phase with
the site area |
HyD |
Contractor |
Contractor
(During Construction Phase) |
|
Ö |
|
|
|
Re-routing
of pedestrian routes through well defined public access |
||||||||||
|
Retaining
and minimizing damage to vegetation where possible. Care shall be taken not to damage those trees identified
in the Tree Survey Report to be retained during the construction phase |
||||||||||
|
Careful and efficient transplanting of existing
vegetation carried out under the supervision of a professional landscape
architect |
||||||||||
Notes:
1.
Des = Design, C = Construction, Op = Operation
2.
EIA Ref = Section number reference in EIA for
Salisbury Road Underpass and Associated Road Improvement Works including Middle
Road Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
Table E4 Summary
of Proposed Mitigation Measures for Landscape and Townscape Impacts (continued)
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures |
Funding
Dept/agent |
Implementation
Dept/agent |
Maintenance
Agent |
Implementation
Stages |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||||
|
Section
8.8 (Temporary Mitigation Measures) |
N/A |
Mitigation for vegetation loss may be achieved in
the form of compensatory planting of transplanting of existing trees in the
area or new plant material as suggested in the Tree Survey Report. This is recommended to be implemented
on the footpaths of Salisbury Road where space allows |
In
place at the commencement of the Construction Phase within the site area, to
be maintained for the duration of Operation Phase |
HyD |
Contractor
(The detailed landscape proposal shall be provided to LCSD for endorsement) |
Contractor
(During Construction Phase) HyD
(first 12 months of operational phase) LCSD
(after first 12 months in operational phase) |
Ö |
|
Ö |
Works
Bureau Technical Circular No. 24/94 |
|
Relocation of existing trees within the site and
where possible, ensuring transplanted trees are to be planted to new position
within the site |
Landscape
Architect / Contractor |
Ö |
|
Ö |
||||||
|
Planting of heavy standard trees along footpaths
of Salisbury Road to create vegetation screen |
||||||||||
|
Detailing of street furniture such as footpath
surfaces and railings to enhance the pedestrian environment |
Contractor |
HyD |
Ö |
Ö |
|
|||||
Notes:
1.
Des = Design, C = Construction, Op = Operation
2.
EIA Ref = Section number reference in EIA for
Salisbury Road Underpass and Associated Road Improvement Works including Middle
Road Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
Table E4 Summary
of Proposed Mitigation Measures for Landscape and Townscape Impacts (continued)
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures |
Funding
Dept/agent |
Implementation
Dept/agent |
Maintenance
Agent |
Implementation
Stages |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||||
|
Section
8.8 (Temporary Mitigation Measures) |
N/A |
Planting of flowering trees and shrubs etc, shall
be considered so as to create colour impacts, strong sense of seasonal
changes and where possible, provide shade for the pedestrians |
In
place at the commencement of the Construction Phase within the site area, to
be maintained for the duration of Operation Phase |
HyD |
Landscape
Architect/Contractor |
Contractor
(During Construction Phase) HyD
(first 12 months of operational phase) LCSD
(after first 12 months in operational phase) |
Ö |
|
Ö |
Works
Bureau Technical Circular No. 24/94 |
Notes:
1.
Des = Design, C = Construction, Op = Operation
2.
EIA Ref = Section number reference in EIA for
Salisbury Road Underpass and Associated Road Improvement Works including Middle
Road Circulation System (Final EIA Report (June 1999))
3. EM&A
Log ref = Section number reference in EM&A Manual
|
|
|
Photo 1 |
Photo 2 |
|
|
|
Photo 3 |
Photo
4 |
Record
Photos for EM&A Works
Contract No. HY/98/22
Supplementary Agreement No. 3
Road Widening Works of Salisbury Road
between Nathan Road and Canton Road
APPENDIX H STANDARD SITE AUDIT CHECKLIST
Project:
Name of inspector: Date:
Time: Weather
condition:
Remarks:
|
Environmental Protection
Measures |
Implemented? Yes/No Please tick (Ö) |
Location of Environmental
Protection Measures |
|
|
Yes |
No |
||
|
Regular watering of exposed site surfaces and
unpaved roads |
|
|
|
|
Frequent watering at dusty static construction
areas and areas close to air sensitive receivers |
|
|
|
|
Provision of side enclosure and covering of
aggregate and/or dusty material |
|
|
|
|
Provision of surface treatment of site hoardings |
|
|
|
|
Provision of tarpaulin covering of dusty vehicle
loads |
|
|
|
|
Provision of vehicle wheel and body washing
facilities |
|
|
|
|
Routing of vehicles and positioning of
construction plant at maximum possible distance from air sensitive receivers |
|
|
|
|
On-site separation of both municipal solid waste
and C&D waste |
|
|
|
|
On-site sorting of construction waste for reuse
and recycling |
|
|
|
|
Relocation of temporary buildings in least
visually prominent locations |
|
|
|
|
Retention of vegetation within the works area |
|
|
|
|
Others (please specify) |
|
|
|
|
|
|
|
|