CONTRACT NO. HY/98/22
SUPPLEMENTARY AGREEMENT NO. 3
ROAD WIDENING WORKS OF SALISBURY
ROAD
BETWEEN NATHAN ROAD AND CANTON ROAD
MONTHLY EM&A REPORT NO. 3
CONTENTS
1.1 Background
1.2 Project
Organisation and Management Structure for EM&A Works
1.3
Contact Details of Key
Management
1.4
Construction Programme
1.5
Works undertaken in May 2002
1.6
Project Works Area
2.0 SUMMARY OF EM&A REQUIREMENTS
2.1
Air Quality
2.2
Noise
2.3
Environmental Mitigation
Measures
3.0 IMPLEMENTATION SCHEDULE OF ENVIRONMENTAL MITIGATION
MEASURES
3.1 Environmental Mitigation
Measures implemented by the Contractor in May 2002
4.1
Air
Quality
4.2
Noise
4.3
Adverse
effects on Air Quality and Noise Level from Non-construction Activities and/or Activities
form other Construction Sites
5.0 RECORD OF NON-COMPLIANCE, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND SUCCESSFUL
PROSECUTIONS
5.1
Non-compliance
5.2
Complaints and Verbal
Complaints
5.3
Notifications of Summons and
Successful Prosecutions
6.1
Potential Environmental
Impacts
6.2
Mitigation Measures
7.0 ADVICE ON THE SOLID AND LIQUID WASTE MANAGEMENT STATUS
7.1
Excess Excavated Materials
7.2
Construction Waste
7.3
Demolition Waste
7.4
Chemical Waste
7.5
General Refuse
8.0 SITE INSPECTION
PROFORMA FOR MAY 2002
APPENDICES
Appendix A Project Organisation Chart and
Management Structure for EM&A Works
Appendix B Construction Programme
Appendix C Project Works Area
Appendix D Dust Monitoring Locations
Appendix E Locations of Air Sensitive
Receivers
Appendix F Implementation Schedule of Environmental Mitigation Measures
Appendix G Record Photos
Appendix H Site Inspection Proforma for May
2002
Appendix I Standard Site Audit Checklist
This is the third EM&A Report
for the project of Road Widening Works of Salisbury Road between Nathan Road
and Canton Road. The contract entitled ¡¥Contract No. HY/98/22, Supplementary
Agreement No. 3, Road Widening Works of Salisbury Road between Nathan Road and
Canton Road¡¦ was awarded to Downer Construction (Hong Kong) Limited in February
2002.
This report mainly presents the
EM&A works undertaken for the captioned project from 1 May 2002 to 31 May
2002.
Air Quality
Site inspection was carried out
once per week by checking the adequacy of the mitigation measures implemented
by the Contractor with reference to the EM&A Manual.
No obvious air quality
deterioration was recorded during the reporting period.
Noise Level
No indication of noise exceedance
was observed during weekly site inspections for this reporting period.
Others
No non-compliance, no
notifications of summons and successful prosecutions were received.
No written and verbal complaints
were received in the month.
Future Key Issues
Future construction activities,
such as pavement and footpath construction, central divider reconstruction,
road furniture and signage installation, resurfacing works, drainage works and
landscaping works will be closely monitored to ensure the effects on air
quality and noise level are minimised.
1.1 Background
Downer Construction (Hong Kong) Limited is the Contractor for the
Supplementary Agreement No. 3 (SA3) for the Contract No. HY/98/22 Road Widening
Works of Salisbury Road between Nathan Road and Canton Road. The road widening
works will provide an additional Salisbury Road southbound lane from Hong Kong
Space Museum to Hong Kong Cultural Centre. Other construction works include
pavement resurfacing, central divider and footpath reconstruction, drainage
works and landscaping works.
The purpose of this report is to report the EM&A works in the period
between 1 May 2002 and 31 May 2002.
1.2 Project Organisation and Management
Structure for EM&A Works
An environmental team (ET)
has been established to investigate and audit the Contractor¡¦s equipment and
work methodologies, to monitor and to audit reports, and to provide
recommendations and improvements. An Independent Environmental Checker (IEC)
has been employed to review the EM&A works by the ET. The Engineer is
generally responsible for supervising the contractor¡¦s activities, reviewing
the EM&A works and mitigation measures. Section 1.4 of the EM&A Manual
can also be referred for the overall works.
The
project organization chart and management structure for EM&A works are
shown in Appendix A.
1.3 Contact
Details of Key Management
Titles,
names and contact telephone numbers of the key personnel of the captioned
project are tabulated below:
|
Title |
Name |
Contact Number |
|
Project Director |
Mr.
Peter Bugden |
2831
8335 |
|
Quality and Environmental Department |
Mr.
Richard Cuta |
2831
8123 |
|
ET ¡V
Babtie Asia Limited (Environmental Consultant) |
Mr.
Mark K.T. Cheung |
2738
3803 |
|
Project
Manager |
Mr.
Ricky Lee |
9252
6252 |
|
Site
Agent |
Mr.
M.W. Suen |
6274
5512 |
|
General
Foreman |
Mr.
K.K. Lau |
6274
3128 |
|
Foreman |
Mr. To
Wing Tak |
6274
5515 |
|
Survey
Team |
Mr.
T.S. Chan |
6274
3633 |
|
Safety
Team |
Mr.
Yuen Wai Ip |
9038
9055 |
1.4 Construction Programme
The latest construction
programme is attached in Appendix B. Environmental protection/mitigation measures
are implemented during the construction phase, the construction programme is
subject to continuous refinement.
1.5 Works undertaken in May 2002
The major
construction activities and works undertaken in May 2002 were as follows:
¡P
Relocation of trees
affected by the road widening works
¡P
Street lighting
installation and diversion at footpath area
¡P
Drainage works
¡P
Resurfacing and
reconstruction of Hong Kong Cultural Centre entry roads and southbound
Salisbury Road
¡P
Central divider
reconstruction
¡P
Reinstatement of pavement
area
¡P
Road furniture and signage
installation at footpath area
1.6 Project
Works Area
The project
works area is shown in Appendix C. The boundary of the works area to the west
of Nathan Road is also given in Appendix C.
2.0 SUMMARY OF EM&A REQUIREMENTS
2.1 Air Quality
According to
Section 1.3 of the EM&A Manual, the captioned project involves minor road
widening works. Because of the short construction period (approximately 6 to 7
months), together with staged construction sequence of works which will limit
the extent of construction area at any one time. Therefore, air quality is
monitored by means of checking the adequacy of dust mitigation measures
implemented by the Contractor (Please refer to Section 2.1 of the EM&A
Manual or Section 2.3.1 of this report for dust mitigation measures). It is
anticipated that proper implementation of dust reduction measures will be
adequate to mitigate dust impacts and maintain Total Suspended Particulate
(TSP) concentration levels within those recommended under the Air Quality
Objectives (AQO) and no further air quality monitoring will be necessary.
All of the dust
monitoring locations identified in the EIA Study is located in the vicinity of
the proposed vehicular underpass (located at the Salisbury Road/Chatham Road
South junction), the monitoring works of which will be carried out as part of
the works east of Nathan Road by KCRC. Hence, the standard requirements of
collating Baseline Monitoring Results, calculation of Action and Limit Levels
etc. have been omitted from this report. These requirements will be fulfilled
under the EM&A for the works east of Nathan Road. Dust monitoring locations adjacent to the project
works area of the captioned project are shown in Appendix D.
Should there be
any obvious air quality deterioration as a result of the construction works,
the ET will perform additional monitoring using, for example, High Volume Sampler (HVS), to measure
TSP concentration levels so as to ensure that any deteriorating air quality can
be readily detected and timely action is to be taken to rectify the situation.
According to
Section 4.1 of the EM&A Manual, regular site inspections are carried out by
the ET at least once per week.
Additional monitoring will be performed
by the ET in the event of complaints from the local residents, and/or any
obvious indication of deterioration of air quality is observed.
2.1.1 Air Sensitive Receivers
According to Section 7.4 of the Final
EIA Report, Peninsula Hotel, YMCA Hotel, Hong Kong Space Museum, Museum of Art
and Hong Kong Cultural Centre are identified as air sensitive receivers. Their
locations are shown in Appendix E.
2.1.2 Air Quality Monitoring
According to
Section 1.3 of the EM&A Manual, it is anticipated that proper
implementation of dust reduction measures (see Section 2.1 of the EM&A Manual
or Section 3.5 of the Final EIA Report for details) will be adequate to
mitigate dust impacts and maintain TSP concentration levels within those
recommended under the Air Quality Objectives (AQO), and no further air quality
monitoring will be necessary.
Should the
Contractor does not implement appropriate dust mitigation measures properly
during construction phase and result in deterioration of air quality, and/or
complaints (including verbal complaints) are received from local residents, the
ET will perform TSP
concentration level measurement.
Monitoring
parameters
1. 24-hour TSP concentration level for
every week
2. 3x1-hour TSP concentration level for
every six days
2.1.3 Monitoring Locations
Dust monitoring locations adjacent to
the project works area of the captioned project are shown in Appendix D.
According to Section 10.1.3 of the Final EIA Report, these dust monitoring
locations are closest to the air sensitive receivers affected by the captioned
project.
2.2 Noise
Though
requirements for noise monitoring has not been specified in the EM&A
Manual, during the course of site inspection carried out by the ET, the ET will
closely monitor construction noise. Should there be any obvious indication of
construction noise level exceedance observed by the ET during site inspections,
the ET will perform additional monitoring and will carry out noise monitoring
works to measure the exceedance of noise level, with reference to the Noise
Control Ordinance. Measurement of construction noise level will be carried out
using an Integrating Sound Level Meter with calibrator which complied with
EPD's requirements.
Additional monitoring will be performed
by the ET in the event of complaints from the local residents, and/or any
obvious indication of construction noise level exceedance is observed.
2.2.1 Noise Sensitive Receivers
According to Section 4.3 of the Final
EIA Report, the noise standards only apply to dwellings relying on opened
windows for ventilation. Since central air-conditioning systems are provided
for all hotels which do not rely on openable windows for ventilation, these
noise sensitive receivers are less sensitive to noise impacts.
2.2.2 Noise Level Monitoring
During the course
of site inspection, the ET will closely monitor construction noise levels.
Should there be
any obvious indication of construction noise level exceedance observed by the
ET during site inspections, and/or complaints (including verbal complaints) are
received from local residents, the ET will perform construction noise
measurement.
Monitoring
parameters
1. Leq (30 min) for the time
period between 0700-1900 hours on normal weekdays
2. L10 and L90 (for
reference)
2.3 Environmental Mitigation Measures
2.3.1 Air Quality
Dust control and
mitigation measures to be implemented during the construction phase are listed
in Section 2.1 of the EM&A Manual and Sections 3.5 and 10.1.7 of the Final
EIA Report. Some environmental mitigation measures are as follows:
¡P
Use of regular watering to reduce dust emissions from exposed site
surfaces and unpaved roads, with complete coverage, particularly during dry
weather.
¡P
Use of frequent watering for
particularly dusty static construction areas and areas close to air quality sensitive
receivers.
¡P
Side enclosure and covering of any
aggregate or dusty material storage piles to reduce emissions. Where this is
not practicable owing to frequent usage, watering should be employed to
aggregate fines.
¡P
Tarpaulin covering of all dusty vehicle
loads transported to, from and between site locations.
¡P
Establishment and use of vehicle wheel
and body washing facilities at the exit points of the site, combined with
cleaning of public roads where necessary.
¡P
Imposition of speed controls for
vehicles and unpaved site roads.
¡P
Where feasible, routing of vehicles and
positioning of construction plant should be at maximum possible distance from
air quality sensitive receivers.
¡P
Instigation of an environmental
monitoring and auditing program to monitor the construction process in order to
enforce controls and modify methods of work if dusty conditions arise.
2.3.2 Noise
According to
Section 4.4 of the Final EIA Report, construction noise level experienced by
the noise sensitive receivers surrounding the project works area are
significantly reduced by with window insulation and central air-conditioning.
If the Contractor implements good site practices listed in Appendix H of the
Final EIA Report, construction noise level experienced by the noise sensitive
receivers will be further reduced. Some of these good site practices are as
follows:
¡P
The Contractor shall comply with and observe the Noise Control Ordinance
and its subsidiary regulations in force in Hong Kong.
¡P
Before the commencement of any work,
the Engineer may require the methods of working, equipment and sound-reducing
intended to be used on the site to be made available for inspection and
approval to ensure that they are suitable for the project.
¡P
The Contractor shall devise, arrange
methods of working and carry out the Works in such a manner so as to minimise
noise impacts on the surrounding environment, and shall provide experienced
personnel with suitable training to ensure that these methods are implemented.
The noise reduction methods shall include, but not be limited to,
scheduling of works, siting of facilities, selection of quiet equipment, and
use of purpose-built acoustic panels and enclosures.
¡P
The Contractor shall ensure that all
plant and equipment to be used on site are properly maintained in good
operating condition and noisy construction activities shall be effectively
sound-reduced by means of silencers, mufflers, acoustic linings or shields,
acoustic sheds or screens or other means to avoid disturbance to any nearby
noise sensitive receivers.
3.0 IMPLEMENTATION SCHEDULE OF ENVIRONMENTAL MITIGATION MEASURES
An
implementation schedule of environmental mitigation measures is attached in
Appendix F.
3.1 Environmental Mitigation Measures
implemented by the Contractor in May 2002
The
Contractor implemented adequate environmental mitigation measures to reduce
dust emissions to the air sensitive receivers adjacent to the project works
area by:
¡P
Tarpaulin covering of
excavated materials stockpiles temporarily stored on site and those on trucks
being transported to dumping sites, to reduce dust emissions during
transportation of dusty materials.
¡P
Removal of surplus excavated
materials from roadside to reduce dust emissions blown up by speedy vehicles.
¡P
Screening of site with
hoardings to reduce dust emissions blown up by strong wind.
¡P
Covering of excavated area
with tarpaulin if works progress is not hindered.
¡P
Aesthetic treatment of some
of the site hoardings to enhance their visual interest and harmony with
surrounding townscape.
¡P
Regular watering of exposed
site surfaces and excavated materials.
The
aforementioned environmental mitigation measures are also listed in Section 2.1
of the EM&A Manual and Section 2.3 of this EM&A Report.
During all site inspections carried out in May 2002,
weather condition is mainly fine. Wind is minimal.
4.1 Air
Quality
As the environmental mitigation measures implemented
by the Contractor during the construction phase are adequate, no Total
Suspended Particulate (TSP) concentration level has to be recorded. Please
refer to photos in Appendix G for implementation of dust reduction measures
done by the Contractor.
Photos in
Appendix G show the environmental mitigation measures implemented by the
Contractor to control dust emissions during this reporting period.
Photo 1 shows
covering of excavated materials to be transported with tarpaulin.
This can effectively
reduce dust emissions when the excavated materials are temporarily stored on
site, as recommended in Section 2.1 of the EM&A Manual.
As tarpaulin covering of the excavation may hinder
works progress during excavation works, or re-routing of utilities, watering
was carried out regularly to reduce dust emissions during excavation, as
recommended in the EM&A Manual (Photo 2).
4.2 Noise
No obvious noise level exceedance was observed during
site inspections.
4.3 Adverse
effects on Air Quality and Noise Level from Non-construction Activities and/or
Activities from other Construction Sites
During the course of site inspection, no adverse
effects on air quality and noise level due to non-construction activities and/or
activities from other construction sites were observed.
5.0 RECORD OF NON-COMPLIANCE, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND
SUCCESSFUL PROSECUTIONS
5.1 Non-compliance
5.1.1 Air quality
No non-compliance was identified during site inspections
as the mitigation measures implemented by the Contractor during site
inspections are adequate.
5.1.2 Noise
No non-compliance in construction noise level was
observed during site inspections.
5.2 Complaints
and Verbal Complaints
No
written and verbal complaints were received in the month.
5.3 Notifications
of Summons and Successful Prosecutions
No notifications
of summons or successful prosecutions were received by the Contractor in the
reporting month.
According to the
latest construction programme attached in Appendix B, the proposed construction
works to be carried out in the next reporting period (June 2002) are as
follows:
¡P
Relocation of trees affected by the road widening works
¡P
Drainage works at Hong Kong Cultural Centre entry roads
¡P
Reconstruction and reinstatement of footpath area outside Hong Kong
Cultural Centre
¡P
Reconstruction of central divider
¡P
Installation of road furniture and road signage
Some of them may
have potential environmental impact and will require mitigation measures, and
such activities will be monitored closely during future site inspections.
6.1 Potential Environmental
Impacts
Potential
environmental impacts on surrounding environment from the aforementioned
construction works are:
¡P
Demolition waste (old drainage pipes) will be produced during drainage
works at Hong Kong Cultural Centre entry roads.
¡P
Demolition waste (old asphalt and concrete) and excavated materials will
be generated due to reconstruction and reinstatement of footpath area outside
Hong Kong Cultural Centre and reconstruction of central divider. The soil
excavated will emit dust if not properly covered.
¡P
Old road furniture and signage are also sources of demolition wastes.
¡P
Operation of plant and equipment during the aforementioned construction
works will deteriorate air quality and increase construction noise level.
¡P
General refuse and office wastes will be produced.
6.2 Mitigation measures
According to
Waste Management Plan and Section 7.3 of this EM&A Report, demolition waste
generated in captioned project will not be reused, and will be transported to
either Tseung Kwan O public filling area or Tolo Harbour Reclamation Area. In
order to minimise environmental impacts of these demolition wastes before and
during transportation, such wastes must be properly covered when temporarily
stored on site before transportation and during transportation for disposal.
General refuse
and office wastes can be reduced by recycling and reuse, please refer to Waste
Management Plan and Section 7.5 of this EM&A Report for details.
The Contractor
can devise, arrange and implement methods of working and carry out the works in
such a manner to minimise noise impacts on surrounding environment. Moreover,
the Contractor must ensure that all plant and equipment to be used on site are
properly maintained in good operating condition and noisy construction
activities must be effectively sound-reduced using silencers, shields or
acoustic sheds. Please refer to Section 2.3.2 of this EM&A Report and
Appendix H of the Final EM&A Report for more details.
7.0 ADVICE
ON THE SOLID AND LIQUID WASTE MANAGEMENT STATUS
The Contractor had carried
out adequate solid and liquid waste management during construction works in
accordance with the revised Waste Management Plan in this reporting period.
The total volume of
construction and demolition (C&D) waste produced in May 2002 was about 130m3.
7.1 Excess
Excavated Materials
The Contractor stockpiles
excavated materials which will be reused for landscaping and backfilling
temporarily on site. These excavated materials are covered with tarpaulin
(please refer to Section 4.1 and Photo 1 of Appendix G for reference).
Excavated materials which
cannot be reused for backfilling were transported to either Tseung Kwan O
public filling area or Tolo Harbour Reclamation Area, according to the Waste
Management Plan. Such materials were covered with tarpaulin, which could
effectively reduce dust emissions during transportation.
7.2 Construction
Waste
According to the Waste
Management Plan, the Contractor separated construction wastes which could be
reused on site and recycled with those to be disposed of. This was carried out
by general workforce under supervision of Foremen and charge hands. For
example, timber (for formwork) was cleaned for reuse, steel was stored for
reuse, reinforcement was sorted into usable lengths for recycling or reuse on
site.
7.3 Demolition
Waste
None of the demolition
waste generated in the captioned project will be reused, according to the Waste
Management Plan. Such waste is transported to either Tseung Kwan O public
filling area or Tolo Harbour Reclamation Area.
7.4 Chemical
Waste
No chemical waste is generated
in the captioned project.
7.5 General
Refuse
The Contractor deposited
aluminium cans, plastic bottles and glass bottles in separately labelled bins
for recycling and reuse.
The
Contractor reduced office wastes through recycling of paper. Signs encouraging
environmental awareness, such as reducing the number of photocopies to a
minimum and using both sides of papers, etc., were put on in the Contractor¡¦s
site office.
8.0 SITE INSPECTION PROFORMA FOR MAY 2002
Site inspection
proforma for May 2002 is attached in Appendix H. Locations of deficiencies are
shown on the site plan attached in Appendix H.
A
standard site audit checklist is attached in Appendix I.
APPENDIX A PROJECT ORGANIATION CHART AND MANAGEMENT
STRUCTURE FOR EM&A WORKS
|
|
Highways Department Contact Person: Mr. Simon C.H. Leung Telephone No.: 2707 7250 ¡P
Overall responsibility of the Project ¡P
Co-ordinate with EPD for decision making for any
non-compliance observed |
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Engineer¡¦s Representative (ER) Contract Person: Mr. Felix Chan Telephone No.: 2605 6262 ¡P
Supervise the Contractor¡¦s activities and ensure that
requirements in the EM&A Manual are fully complied with ¡P
Inform the Contractor when action is required to
reduce impacts ¡P
Review the EM&A works performed by the ET |
|
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Environmental Protection Department (EPD) (EM&A Section) Contact Person: Mr. Anthony Y.K. Ho Telephone No.: 2835 1871 ¡P
Regulatory body ¡P
EM&A approval |
|
|
The Contractor Contact Person: Mr. M.W. Suen (Site Agent) Telephone No.: 9202 9341 ¡P
Employ the ET to undertake monitoring, and
reporting of EM&A ¡P
Provide assistance to the ET in carrying out
monitoring ¡P
Implement measures to reduce impact |
||
|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Independent Environmental Checker (IEC) Contact Person: Mr. Tim Cramp Telephone No.: 2893 1551 ¡P
Review the EM&A works performed by the ET ¡P
Audit monitoring activities and results ¡P
Review the EM&A reports submitted by the ET |
|
|
Environmental Team (ET) Contact Person: Mr. Mark K.T. Cheung Telephone No.: 2738 3803 ¡P
Monitor the various environmental parameters as
required in the EM&A Manual ¡P
Carry out site inspections to investigate and
audit the Contractor¡¦s site practices, equipment and work methodologies with
respect to pollution control and environmental mitigation and anticipate
environmental issues for proactive action before problems arise ¡P
Audit and prepare audit reports on the
environmental monitoring data and the site environmental conditions |
||
|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
|
|
|
|
|
Supplementary
Agreement No. 3
Road
Widening Works of Salisbury Road
between Nathan
Road and Canton Road

Management
Structure for EM&A Works
Supplementary
Agreement No. 3
Road
Widening Works of Salisbury Road
between
Nathan Road and Canton Road
APPENDIX B CONSTRUCTION PROGRAMME







APPENDIX
D DUST MONITORING
LOCATIONS

APPENDIX
E LOCATIONS OF
AIR SENSITIVE RECEIVERS

APPENDIX
F IMPLEMENTATION
SCHEDULE OF ENVIRONMENTAL MITIGATION MEASURES
The
schedule of implementation of the recommended mitigation measures for various
environmental aspects are presented in Tables F1 and F4 for different
environmental aspects
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures/Timing of completion of Measures |
Implementation
Dept/agent |
Implementation
Stage |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||
|
Section
3.5 |
Section
2.1 |
Established
standards and guidelines with EPD¡¦s recommended pollution control clauses
should be incorporated in the contract documents |
During
Construction Phase within the site area |
Contractor |
Ö |
Ö |
|
|
|
Dust
reduction measures while carrying out construction works in accordance with
the Air Pollution Control (Construction Dust) Regulation to minimise the dust
emission from the construction site |
Ö |
Ö |
|
TM
on EIA Process, APCO, Air Pollution Control (Construction Dust) Regulation |
||||
Notes:
1.
Des = Design, C = Construction, O = Operation
2.
EIA Ref = Section number reference in EIA for Salisbury
Road Underpass and Associated Road Improvement Works including Middle Road
Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
Table F2 Summary
of Proposed Mitigation Measures for Construction Waste Management
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures/Timing of completion of Measures |
Implementation
Dept/agent |
Implementation
Stage |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||
|
Section
6.3 |
Section
3.1 |
On-site
separation of both municipal solid waste and C&D waste should be
conducted as far as possible.
Construction waste should be sorted on-site into construction & demolition
waste and public fill fraction for re-use and recycling as far as practical |
During
Construction Phase within the site area |
Contractor |
Ö |
Ö |
Ö |
TM
on EIA Process, WDO |
|
Waste
management measures would be proposed in accordance with the Criteria for
Evaluating Waste Management Implications stipulated in Annex 7 of the TM EIAO
and follow the Guidelines for Assessment of Waste Management Implications
stated in Annex 15 of the TM EIAO as appropriate |
||||||||
|
Standard
C&D materials management clause should be included in the construction
contact |
||||||||
Notes:
1.
Des = Design, C = Construction, O = Operation
2.
EIA Ref = Section number reference in EIA for Salisbury
Road Underpass and Associated Road Improvement Works including Middle Road
Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
Table F3 Summary
of Proposed Mitigation Measures for Visual Impact
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures |
Funding
Dept/agent |
Implementation
Dept/agent |
Maintenance
Agent |
Implementation
Stages |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||||
|
Section
8.7 (Temporary Mitigation Measures |
N/A |
Screening
of site works by hoardings |
In
place at the commencement and for the duration of the Construction Phase with
the site area |
HyD |
Contractor |
Contractor
(During Construction Phase) |
Ö |
Ö |
|
|
|
Surface
treatment of site hoardings to enhance their visual interest and harmony with
surrounding landscape/townscape |
|
|
|
|||||||
|
Locating
temporary buildings (e.g. Site office) in least visually prominent locations |
Design
Engineer/Contractor |
|
Ö |
|
||||||
|
Retention
of vegetation within the works site area where possible |
Landscape
Architect / Contractor |
Ö |
Ö |
|
||||||
|
Provision
of fences around all the low, circular raised planters to ensure that materials
and debris will not be dumped on tree roots |
Contractor |
|
Ö |
|
||||||
|
Footpaths
along south side of Salisbury Road will be replanted with heavy standard
trees where possible. The proposed
planning will also reprovide shading along the footpath temporarily removed
during the construction stage |
In
place by the completion of Construction Phase within the site area, to be
maintained for the duration of Operation Phase |
HyD |
Landscape
Architect/Contractor |
Contractor
(During construction phase) LCSD
(during operation phase) |
Ö |
|
Ö |
|
||
Notes:
1.
Des = Design, C = Construction, O = Operation
2.
EIA Ref = Section number reference in EIA for
Salisbury Road Underpass and Associated Road Improvement Works including Middle
Road Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
Table F4 Summary
of Proposed Mitigation Measures for Landscape and Townscape Impacts
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures |
Funding
Dept/agent |
Implementation
Dept/agent |
Maintenance
Agent |
Implementation
Stages |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||||
|
Section
8.8 (Temporary Mitigation Measures |
N/A |
Re-routing
of pedestrian routes away from the work site where possible |
In
place at the commencement and for the duration of the Construction Phase with
the site area |
HyD |
Contractor |
Contractor
(During Construction Phase) |
|
Ö |
|
|
|
Re-routing
of pedestrian routes through well defined public access |
||||||||||
|
Retaining
and minimizing damage to vegetation where possible. Care shall be taken not to damage those trees identified
in the Tree Survey Report to be retained during the construction phase |
||||||||||
|
Careful and efficient transplanting of existing vegetation
carried out under the supervision of a professional landscape architect |
||||||||||
Notes:
1.
Des = Design, C = Construction, O = Operation
2.
EIA Ref = Section number reference in EIA for
Salisbury Road Underpass and Associated Road Improvement Works including Middle
Road Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
Table F4 Summary
of Proposed Mitigation Measures for Landscape and Townscape Impacts (continued)
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures |
Funding
Dept/agent |
Implementation
Dept/agent |
Maintenance
Agent |
Implementation
Stages |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||||
|
Section
8.8 (Temporary Mitigation Measures) |
N/A |
Mitigation for vegetation loss may be achieved in
the form of compensatory planting of transplanting of existing trees in the
area or new plant material as suggested in the Tree Survey Report. This is recommended to be implemented
on the footpaths of Salisbury Road where space allows |
In
place at the commencement of the Construction Phase within the site area, to
be maintained for the duration of Operation Phase |
HyD |
Contractor
(The detailed landscape proposal shall be provided to LCSD for endorsement) |
Contractor
(During Construction Phase) HyD
(first 12 months of operational phase) LCSD
(after first 12 months in operational phase) |
Ö |
|
Ö |
Works
Bureau Technical Circular No. 24/94 |
|
Relocation of existing trees within the site and where
possible, ensuring transplanted trees are to be planted to new position
within the site |
Landscape
Architect / Contractor |
Ö |
|
Ö |
||||||
|
Planting of heavy standard trees along footpaths
of Salisbury Road to create vegetation screen |
||||||||||
|
Detailing of street furniture such as footpath
surfaces and railings to enhance the pedestrian environment |
Contractor |
HyD |
Ö |
Ö |
|
|||||
Notes:
1.
Des = Design, C = Construction, O = Operation
2.
EIA Ref = Section number reference in EIA for Salisbury
Road Underpass and Associated Road Improvement Works including Middle Road
Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
Table F4 Summary
of Proposed Mitigation Measures for Landscape and Townscape Impacts (continued)
|
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration of measures |
Funding
Dept/agent |
Implementation
Dept/agent |
Maintenance
Agent |
Implementation
Stages |
Relevant
Legislation and Guidelines |
||
|
Des |
Con |
Op |
||||||||
|
Section
8.8 (Temporary Mitigation Measures) |
N/A |
Planting of flowering trees and shrubs etc, shall
be considered so as to create colour impacts, strong sense of seasonal changes
and where possible, provide shade for the pedestrians |
In
place at the commencement of the Construction Phase within the site area, to
be maintained for the duration of Operation Phase |
HyD |
Landscape
Architect/Contractor |
Contractor
(During Construction Phase) HyD
(first 12 months of operational phase) LCSD
(after first 12 months in operational phase) |
Ö |
|
Ö |
Works
Bureau Technical Circular No. 24/94 |
Notes:
1.
Des = Design, C = Construction, O = Operation
2.
EIA Ref = Section number reference in EIA for
Salisbury Road Underpass and Associated Road Improvement Works including Middle
Road Circulation System (Final EIA Report (June 1999))
3.
EM&A Log ref = Section number reference in
EM&A Manual
|
|
Photo 1
|
|
|
|
Photo 2 |
Record Photos for EM&A Works
Contract No. HY/98/22
Supplementary Agreement No. 3
Road Widening Works of Salisbury Road
between Nathan Road and Canton Road
APPENDIX
I STANDARD SITE
AUDIT CHECKLIST
Project:
Name of inspector: Date:
Time: Weather
condition:
Remarks:
|
Environmental Protection
Measures |
Implemented? Yes/No Please tick (Ö) |
Location of Environmental
Protection Measures |
|
|
Yes |
No |
||
|
Regular watering of exposed site surfaces and
unpaved roads |
|
|
|
|
Frequent watering at dusty static construction
areas and areas close to air sensitive receivers |
|
|
|
|
Provision of side enclosure and covering of
aggregate and/or dusty material |
|
|
|
|
Provision of surface treatment of site hoardings |
|
|
|
|
Provision of tarpaulin covering of dusty vehicle
loads |
|
|
|
|
Provision of vehicle wheel and body washing
facilities |
|
|
|
|
Routing of vehicles and positioning of construction
plant at maximum possible distance from air sensitive receivers |
|
|
|
|
On-site separation of both municipal solid waste
and C&D waste |
|
|
|
|
On-site sorting of construction waste for reuse
and recycling |
|
|
|
|
Relocation of temporary buildings in least
visually prominent locations |
|
|
|
|
Retention of vegetation within the works area |
|
|
|
|
Others (please specify) |
|
|
|
|
|
|
|
|