Major Projects

Improvements to Island Eastern Corridor section between North Point Interchange and Sai Wan Ho

(updated as at 31.05.2007)

Contract Title :

HY/99/15 – Improvements to Island Eastern Corridor section between North Point Interchange and Sai Wan Ho

Contractor :

Gammon Construction Limited.

Construction Commencement Date :

July 2000

Commissioning Date :

July 2003

Contract Value ($Million):

688

Description :

The project includes :

  1. construction of a 800-metre long section of two-lane elevated      carriageway in the eastbound direction between Man Hong Street and Eastern Harbour Crossing (EHC);
  2. construction of a 1.4-kilometre long section of single-lane arriageway including a 400-metre long section of elevated carriageway and a 45-metre long section underpass in the westbound direction from Tai Cheong Street at Sai Wan Ho to the west of EHC;
  3. construction of 2 additional slip roads for the westbound traffic each from Kornhill Flyover and the Sai Wan Ho slip road, and realignment of the existing slip road at Taikoo Shing Interchange; and
  4. construction of various sections of carriageway at grade, recreational facilities along a promenade and other ancillary works including drainage, landscaping, retaining wall, traffic aids, lighting and street furniture.