Design and Build of Traffic Improvements to Tuen Mun Road Town Centre Section

(updated as at 31.12.2011)

Contract Title :

HY/2009/03 – Design and Build of Traffic Improvements to Tuen Mun Road Town Centre Section

Consultant :

AECOM Asia Company Limited

Contractor :

China Harbour Engineering Company Limited

Construction Commencement Date :

26 Feb 2010

Completion Date :

End 2013 (Anticipated)

Contract Sum ($Million) :

1548

Description :

  1. Widening of the TMRTCS between Yan Oi Town Square and Wong Chu Road of approximately 1.5 km long from a dual 2-lane carriageway to a dual 3-lane carriageway;
  2. Resurfacing of existing section of TMR;
  3. Construction of a single-lane flyover of approximately 450 m long, which extends from Tuen Hing Road and runs along Tsing Hoi Circuit to merge eventually with the TMR Kowloon-bound carriageway;
  4. Reconstruction of four existing footbridges;
  5. Construction of noise barriers and enclosures;
  6. Improvement of three existing traffic signal controlled junctions along Castle Peak Road between Tuen Hing Road and Hoi Wing Road; and
  7. Associated civil, structural, landscaping, geotechnical works, and works on reprovisioning of existing facilities, environmental mitigation, drainage, road lighting, water mains and traffic aids.