Contract No. HY/2009/11 – Central – Wan Chai Bypass – North Point Reclamation |
| Contract
Title : |
| Central – Wan Chai Bypass – North Point Reclamation |
| |
| Consultant : |
AECOM Asia Company Limited
(Formerly known as Maunsell Consultants Asia Ltd.) |
| |
| Contractor : |
| China Harbour Engineering Company Ltd and China Road and Bridge Corporation Joint Venture |
| |
| Construction
Commencement Date : |
18 December 2009
|
| |
| Completion Date : |
Third quarter of 2011 |
| |
| Contract
Sum ($Million) : |
303.132 |
| |
|
|
| |
|
| Description : |
The scope of the contract mainly includes:
- construction of permanent seawall and reclamation (about 3.3 hectares) at North Point between Power Street and the breakwater near Hing Fat Street;
- construction of temporary open channel connecting the outfalls along the existing seawall to new outfalls; and
- modification of stormwater drainage system at Oil Street.
|
|