Contract Title :

HY/2008/12 – Bus-bus Interchanges on Tuen Mun Road

Consultant :

AECOM Asia Company Limited

Contractor :

Leader Civil Engineering Co. Ltd.

Construction Commencement Date :

15 July 2010

Commissioning Date :

Mid 2013

Contract Sum ($Million) :

144.9

Description :

The scope of the contract mainly includes :

  1. the construction of a bus-bus interchange on Tuen Mun Road Kowloon-bound near Siu Lam Interchange;
  2. the construction of a bus-bus interchange on Tuen Mun Road Tuen Mun-bound near Tai Lam Kok roundabout;
  3. the widening of Brothers' Bridge;
  4. the construction of a link bridge with two lifts; and
  5. associated civil works including road reconstruction, provision of shelters, drainage, landscaping, traffic aids and street lighting, slope works, waterworks, and provisioning works for traffic control and surveillance.