


TABLE OF CONTENTS
3.1 Summary of
Inspection – 14th August 2008
3.1.1 Planting
Works and Maintenance Operations
4.1 Bi-monthly
Audit Schedule during Establishment Period
Appendices
1.0
INTRODUCTION
This is a Landscape and Visual Audit conducted to fulfill the requirements of the EIA during the Operational Phase of the project, and is based on the procedures and requirements as set out in the Environmental Monitoring and Audit Manual prepared under Agreement No. CE98/98 Preliminary Design and Ground Investigation for Widening of Yuen Long Highway between Lam Tei and Shap Pat Heung Interchange.
Under the Environmental Impact Assessment for the above, the proposed mitigation measures included both the compensatory planting works and treatment to structures. As stated in paragraphs 5.3.2 & 5.3.3 of the EM&A Manual, all landscape mitigation measures undertaken by the Contractor during the first 12 months of the Operational Phase shall be audited on a bi-monthly basis to ensure compliance with the intended aims of the mitigation measures.
2.0 SCOPE OF AUDIT
The broad scope of the audit on mitigation measures is as detailed below:
2.1
Compensatory Planting
Operation Phase:
·
Monitoring of the maintenance operations to ensure
all plants are well developed and grow during the Establishment Period.
3.0 INSPECTIONS
3.1
Summary of Inspection
3.1.1 Planting Works and Maintenance Operations
General Observations:
·
It was generally observed that the Contractor had
carried out the followings works since the last inspection in June:
-
replacement of many of the dead / broken / missing
trees;
-
carried out grass cutting to all slope areas;
-
planting of additional shrubs into shrub planting
areas;
-
carried out woodland mix planting to some
outstanding areas.
·
It was observed that the Contractor had partially updated
the as-built drawings to reflect the actual site conditions of all trees
planted on site.
·
It was observed a number of trees on site were
rocked loose by the recent Typhoon, the Contractor was requested to re-stake
all loose / leaning trees.
·
A detailed summary of the inspection was noted on
the drawings enclosed under Appendix A.
Woodland Mix Planting:
·
It was observed that no planting work was carried
out as replacement for missing tree and shrub species as specified in the
·
Planting of Woodland Mix for other slope areas
identified to be devoid of vegetation at the last inspection was still
outstanding.
Amenity Tree Planting:
·
It was observed that the Contractor had carried out trees
replacement planting for some of the dead and missing trees. However, it was noted that there are
still quite a number of trees still to be replaced. The Contractor was reminded to replace
all dead and undersized trees as soon as possible.
Amenity Shrub Planting:
·
It was observed that the Contractor had carried out
additional planting of shrubs to planting areas as previously identified. However, it was still considered that
the additional shrub quantities planted as replacement to be insufficient. The Contractor was reminded to rectify
the shrubs to quantities as specified on drawings.
Berm Planters:
·
It was observed that the Contractor had replaced
some of the dead trees previously found on berm planters. However, a number of dead and broken
trees were still observed on site. The
Contractor was reminded to replace all remaining trees as soon as possible.
·
It was observed that the Contractor had planted
whips, shrubs, and climber plants of Berm Planter Mixes to all Berm Planter
areas. However, there were some
dead plants observed. The
Contractor was reminded to replace all dead plants as soon as possible.
Transplanted Trees:
·
It was observed that the Contractor had revised the
drawings to show actual locations of the transplanted trees.
Existing Retained Trees:
·
It was observed that the Contractor had transplanted
back the trees 1044 and 1046 which are stated as Existing Tree to be Retained on the drawing.
3.1.2 Recommendations
·
The Contractor was reminded to perform all landscape
maintenance operations as stipulated in the General Specification and
Particular Specification to ensure the healthy establishment of all the trees,
shrubs, and groundcover plants.
·
The Contractor was reminded to replace all remaining
dead and undersized trees and any other trees found to be in poor conditions
prior to the next site inspection.
·
The Contractor was again reminded to rectify all
woodland mix planting areas through infill planting for all missing trees and
shrub species to the specified quantities.
Also, the Contractor was reminded to carry out planting of woodland mix
plants to the outstanding areas.
·
The Contractor was reminded to further rectify all
shrub amenity planting areas by re-planting all missing shrubs and where the
actual quantities are less than that specified.
·
The Contractor was reminded to carry out regular
inspection of all tree stakes, especially trees on berm planters where it could
be easily blown over in strong wind conditions, and rectify all defects as soon
as possible.
·
The Contractor was reminded to replace all dead
plants of ‘Berm Planter Mixes’ on Berm Planters.
·
The Contractor was reminded to continue grass
cutting and weeding of all slopes, including removal of undesired self-seeded Leucaena leucocephala species on a
regular basis. Also, the Contractor
to carry out fertilizing of plants, etc.
4.0 AUDIT SCHEULE
4.1 Bi-monthly Audit Schedule during Establishment Period
The next bi-monthly audit is
scheduled to be conducted on 16th October
2008.
Appendix A