


TABLE OF CONTENTS
3.1 Summary of Inspection – 12th
June 2008
3.1.1 Planting Works and Maintenance
Operations
4.1 Bi-monthly Audit Schedule
during Establishment Period
Appendices
Appendix A Detailed Summary of
the Inspection
This is a Landscape and Visual Audit conducted to fulfill the
requirements of the EIA during the Operational Phase of the project, and is
based on the procedures and requirements as set out in the Environmental
Monitoring and Audit Manual prepared under Agreement No. CE98/98 Preliminary
Design and Ground Investigation for Widening of Yuen Long Highway between Lam
Tei and Shap Pat Heung Interchange.
Under
the Environmental Impact Assessment for the above, the proposed mitigation
measures included both the compensatory planting works and treatment to
structures. As stated in paragraphs
5.3.2 & 5.3.3 of the EM&A Manual, all landscape mitigation measures
undertaken by the Contractor during the first 12 months of the Operational
Phase shall be audited on a bi-monthly basis to ensure compliance with the
intended aims of the mitigation measures.
The broad scope of the audit on
mitigation measures is as detailed below:
Operation Phase:
·
Monitoring
of the maintenance operations to ensure all plants are well developed and grow
during the Establishment Period.
General Observations:
·
It was
basically observed that no landscape maintenance operations were carried out by
the Contractor over the last 2 months, except for the grass cutting of slope
feature no. 6NW-D/F18.
·
An
additional 30 more trees were observed dead, with a couple of more trees leaning
/ fallen over since the last inspection.
·
A
detailed summary of the inspection was noted on the drawings enclosed under
Appendix A.
Woodland Mix Planting:
·
Replacement
planting of missing tree and shrub species as specified in the Woodland Mix was
outstanding.
·
Planting
of Woodland Mix for the few slope areas identified to be devoid of plants at
the last inspection was outstanding.
Amenity Tree Planting:
·
Rectification
of a number of planted trees to locations as shown on drawings was outstanding.
·
Replacement
planting for over 270 dead trees, more than 110 trees of wrong species, and
over 250 trees unaccounted for at the last inspection was outstanding.
·
Replacement
planting of Schefflera heptaphylla
trees for all the incorrectly planted Schefflera
actinophylla tree species was outstanding.
·
Replacement
planting of Bauhinia variegata trees
for all the incorrectly planted Bauhinia
purpurea or Bauhinia blakeana
tree species was outstanding.
Amenity Shrub Planting:
·
Replacement
planting for all missing shrubs and groundcovers plants was outstanding.
Berm Planters:
·
Replacement
planting for all incorrectly planted tree species and 104 missing trees in berm
planters was outstanding.
·
Replacement
of over 20 dead trees planted in all berm planters as identified at the
previous inspection was outstanding.
·
Replanting
of whips, shrubs, and climber plants of Berm Planter Mixes for all the berm
planters was outstanding.
Transplanted Trees:
·
Revised
drawings to show actual locations of some of the transplanted trees were
outstanding.
Existing Retained Trees:
·
As
noted in the last inspection where existing trees to be retained as shown on
Dwg. No. 01206/1630L was missing, the Contractor had now transplanted 10 trees
back into locations of existing trees to be retained. The Contractor was requested to provide
documentation that instruction from RE was obtained for transplanting of those
trees to allow for the works and its subsequent re-instatement.
·
The
Contractor was strongly recommended to perform all landscape maintenance
operations as stipulated in the General Specification and Particular
Specification to ensure the healthy establishment of all the trees, shrubs, and
groundcover plants, i.e., cutting of overgrown grass and removal of weeds on
all slopes; replace all dead trees; replant all missing trees, seedling trees,
shrubs and groundcover plants; re-staking all trees with broken / leaning tree
stakes; pruning of die back tree branches; fertilizing of plants, etc.
·
The
Contractor was reminded to replant altogether over 600 new trees as replacement
for all dead trees, trees of wrong species planted, missing trees, and any
other trees found to be in poor conditions prior to the next site inspection.
·
The
Contractor was reminded to rectify all woodland mix planting areas through
infill planting for all missing trees and shrub species to the specified
quantities. Also, the Contractor
was reminded to carry out planting of woodland mix plants to the outstanding
areas.
·
The
Contractor was reminded to rectify all shrub amenity planting areas by
re-planting all missing shrubs and where the actual quantities are less than
that specified.
·
The
Contractor was reminded to carry out regular inspection of all tree stakes,
especially trees on berm planters where it could be easily blown over in strong
wind conditions, and rectify all defects as soon as possible.
·
The
Contractor was reminded to re-plant all ‘Berm Planter Mixes’ plants in the Berm
Planters.
·
The
Contractor was requested to clarify the status of all missing retained trees.
·
The
Engineer was reminded to revise the drawings to show the actual locations of
transplanted trees.
The next bi-monthly
audit is schedule to be conducted on 14th August 2008.