Reconstruction and Improvement of Tuen Mun Road – Sam Shing Hui Section
(updated as at 31.3.2012)
Contract Title :
HY/2008/11 – Reconstruction and Improvement of Tuen Mun Road – Sam Shing Hui Section
Consultant :
AECOM Asia Company Limited
(Formerly known as Maunsell Consultants Asia Ltd.)
Contractor :
China Harbour Engineering Company Limited
Construction Commencement Date :
30 June 2009
Commissioning Date :
End 2014
Contract Sum ($Million) :
1366
Description :
The Contract ”Reconstruction and Improvement of Tuen Mun Road – Sam Shing Hui Section” comprises 4.7km dual 3-lane carriageway from Siu Lam to Sam Shing Hui.
The scope of the contract mainly includes:
- reconstruction and re-alignment of Tuen Mun Road between Siu Lam and Sam Shing Hui to current expressway standard;
- widening of traffic lanes to expressway standard width and provision of hard shoulders and verges along Tuen Mun Road;
- widening of highways structures including vehicular bridges, box culverts and subways;
- replacement of the existing road restraint system with new types of parapets and roadside barriers;
- reconstruction of road pavements;
- installation of noise enclosure; and
- ancillary works including slope, drainage, landscaping, utility works; installation of traffic control and surveillance and fire fighting systems; modification of directional signs to current expressway standard; and provision of catchwater decking and natural terrain hazard mitigation measures.
For more information, please visit Contract Web Site.